Greenfield (SPRINGERVILLE - VAIL)

Greenfield

Greenlee County, Arizona · SPP

DC Readiness
58.2
Good / 100

Greenfield (SPRINGERVILLE - VAIL) is a greenfield datacenter candidate site in Greenlee County, Arizona, interconnecting through SPP. It screens at 58.2/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationSPRINGERVILLE
Substation voltage345 kV
Available capacity600 MW
LMP zoneSPP_SOUTH
Wholesale LMP$15.62/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth24
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPLogin Tucson
IXP distance119.8 mi
Fiber providers3
Fiber coverage48.6%
Nearest cloud providerAzure
Nearest cloud regionwestus3
Cloud region distance172.8 mi

Site characteristics

Site typeGreenfield
Parcel ownerDEMING ELECTRIC POWER COOPERATIVE
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub

Risk & environment

Flood zoneZone X
Water stress (WRI)4.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score78/100
Construction cost index122.3 (avg 100)

Location context

Nearest datacenterDirecTV DC
DC distance99.7 mi
Nearest rail8.0 mi
Nearest gas pipeline6.1 mi
Nearest fiber route116.6 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (property_tax_reduction)
Commercial electricity11.00¢/kWh
Industrial electricity8.60¢/kWh
Cooling degree days3,400
Heating degree days1,500
Land price / acre$5,515

Incentive detail: Government Property Lease Excise Tax (GPLET) for qualified facilities on government land.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
49
Fiber connectivity12%
57
Energy cost10%
91
Water risk8%
31
Natural hazard8%
78
Buildability7%
70
Labor market4%
50
DC cluster4%
25
Land / acreage3%
46
Construction cost3%
48
Gas pipeline2%
81
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Greenlee County, ranked by DC Readiness.

Sites near Greenfield (SPRINGERVILLE - VAIL)
SiteTypeVoltageCapacityQueue waitScore
GREENLEESubstation-Adjacent345 kV600 MW3.5 yrs64.9
MORENCISubstation-Adjacent230 kV300 MW5.7 yrs62.0
Greenfield (SPRINGERVILLE - VAIL)Greenfield345 kV600 MW3.5 yrs59.3
Greenfield (SPRINGERVILLE - VAIL)Greenfield345 kV600 MW3.5 yrs58.9
Greenfield (SPRINGERVILLE - VAIL)Greenfield345 kV600 MW3.5 yrs57.2
Greenfield (GREENLEE - WINCHESTER)Greenfield345 kV600 MW5.7 yrs56.3
Greenfield (SPRINGERVILLE - VAIL)Greenfield345 kV600 MW3.5 yrs54.9
Greenfield (HACKBERRY - MORENCI)Greenfield230 kV300 MW5.7 yrs54.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.