Mississippi County has 39 scored datacenter candidate sites averaging 55.6/100 DC Readiness, with a catalogued aggregate of 7,608 MW. FEMA rates local natural-hazard risk as "Relatively High".
39
Candidate sites
55.6/100
Avg DC Readiness
7,608 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Mississippi County
No
Datacenter tax incentive
10.05¢/kWh
Commercial electricity
6.85¢/kWh
Industrial electricity
5
Fiber providers
Low
Water stress
$4,584
Land price / acre
1,900
Cooling degree days
3,400
Heating degree days
60°F
Mean annual temp
By site type
Top datacenter sites in Mississippi County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| DELL POWER STATION | Substation-Adjacent | 500 kV | 1,000 MW | 1.4 yrs | 70.6 |
| DELL | Substation-Adjacent | 500 kV | 1,000 MW | 1.4 yrs | 68.6 |
| PLUM POINT ENERGY STATION | Substation-Adjacent | 500 kV | 1,000 MW | 1.4 yrs | 67.6 |
| UNKNOWN107704 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 63.3 |
| Greenfield (DELL - JONESBORO EHV) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 62.8 |
| UNKNOWN121084 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 62.5 |
| UNKNOWN121082 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 62.3 |
| UNKNOWN108138 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 62.3 |
| UNKNOWN108136 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 62.1 |
| Greenfield (WEST NEW MADRID - DELL) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 61.5 |
| UNKNOWN108142 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 61.3 |
| UNKNOWN107706 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 60.9 |
| UNKNOWN121083 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 60.8 |
| UNKNOWN108138 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 59.1 |
| Greenfield (UNKNOWN108136 - UNKNOWN121082) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 57.2 |
| Greenfield (DELL - JONESBORO EHV) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 57.1 |
| EC Near Osceola (AR) | Greenfield | — | — | 1.4 yrs | 56.6 |
| EC Near Osceola (AR) | Greenfield | — | — | 1.4 yrs | 56.5 |
| EC Near Osceola (AR) | Greenfield | — | — | 1.4 yrs | 56.5 |
| Greenfield (UNKNOWN117319 - DELL) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 56.4 |
| EC Near Osceola (AR) | Greenfield | — | — | 1.4 yrs | 56.4 |
| EC Near Osceola (AR) | Greenfield | — | — | 1.4 yrs | 56.3 |
| UNKNOWN107708 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 56.2 |
| Greenfield (UNKNOWN108136 - UNKNOWN117275) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 56.0 |
| Greenfield (UNKNOWN121083 - DELL) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 55.6 |
Mississippi County datacenter FAQ
- How many datacenter sites are in Mississippi County?
- 39 scored datacenter candidate sites, averaging 55.6/100 DC Readiness.
- Does Mississippi County offer datacenter tax incentives?
- No datacenter-specific tax incentive is on record for Mississippi County in our dataset.
- What is the natural-hazard risk in Mississippi County?
- FEMA's National Risk Index rates Mississippi County as "Relatively High" (score 38).
- What are industrial electricity rates in Mississippi County?
- Average industrial electricity is 6.85¢/kWh and commercial is 10.05¢/kWh in Mississippi County.