Datacenter Sites in Nevada, Arkansas
Nevada has 15 scored datacenter candidate sites averaging 59.3/100 DC Readiness, with a catalogued aggregate of 4,800 MW. FEMA rates local natural-hazard risk as "Relatively High".
15
Candidate sites
59.3/100
Avg DC Readiness
4,800 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Nevada
No
Datacenter tax incentive
11.65¢/kWh
Commercial electricity
7.45¢/kWh
Industrial electricity
4
Fiber providers
Low
Water stress
$2,507
Land price / acre
1,900
Cooling degree days
3,400
Heating degree days
60°F
Mean annual temp
By site type
Top datacenter sites in Nevada
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| Greenfield (UNKNOWN107970 - HOT SPRING GEN) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 66.8 |
| TAP142011 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 66.3 |
| TAP150158 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 65.8 |
| Greenfield (UNKNOWN107970 - HOT SPRING GEN) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 65.7 |
| Greenfield (UNKNOWN107970 - HOT SPRING GEN) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 63.4 |
| Greenfield (UNKNOWN107970 - HOT SPRING GEN) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 61.6 |
| UNKNOWN107715 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 61.0 |
| OZ Nevada | Greenfield | — | — | 1.4 yrs | 60.5 |
| Greenfield (UNKNOWN108083 - TAP142011) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 59.2 |
| TAP150158 | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 57.9 |
| Greenfield (UNKNOWN121730 - TAP150158) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 57.6 |
| Greenfield (UNKNOWN121730 - UNKNOWN157874) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 54.8 |
| Greenfield (UNKNOWN107715 - TAP142011) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 52.4 |
| EC FFE Nevada County | Greenfield | — | — | 1.4 yrs | 52.1 |
| Mine Site | Former Mine | — | — | — | 44.4 |
Nevada datacenter FAQ
- How many datacenter sites are in Nevada?
- 15 scored datacenter candidate sites, averaging 59.3/100 DC Readiness.
- Does Nevada offer datacenter tax incentives?
- No datacenter-specific tax incentive is on record for Nevada in our dataset.
- What is the natural-hazard risk in Nevada?
- FEMA's National Risk Index rates Nevada as "Relatively High" (score 38).
- What are industrial electricity rates in Nevada?
- Average industrial electricity is 7.45¢/kWh and commercial is 11.65¢/kWh in Nevada.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Nevada, Arkansas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.