Greenfield (INDEPENDENCE SUBSTATION - JONE)

Greenfield

Poinsett County, Arkansas · MISO

DC Readiness
63.3
Good / 100

Greenfield (INDEPENDENCE SUBSTATION - JONE) is a greenfield datacenter candidate site in Poinsett County, Arkansas, interconnecting through MISO. It screens at 63.3/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationINDEPENDENCE SUBSTATION
Substation voltage500 kV
Available capacity1,000 MW
LMP zoneMISO_ARKANSAS
Wholesale LMP$30.14/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth161
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPARE-ON Forrest City
IXP distance47.0 mi
Fiber providers6
Fiber coverage61.7%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance391.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerCraighead Rice Milling Co
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone A (SFHA)
Water stress (WRI)0.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score47/100
Construction cost index69.0 (avg 100)

Location context

Nearest datacenterARE-ON Forrest City
DC distance47.0 mi
Nearest rail4.8 mi
Nearest gas pipeline4.6 mi
Nearest fiber route201.8 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveNo
Commercial electricity11.08¢/kWh
Industrial electricity11.42¢/kWh
Cooling degree days1,900
Heating degree days3,400
Land price / acre$4,440

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
72
Speed to power15%
48
Fiber connectivity12%
64
Energy cost10%
89
Water risk8%
83
Natural hazard8%
47
Buildability7%
65
Labor market4%
50
DC cluster4%
40
Land / acreage3%
48
Construction cost3%
93
Gas pipeline2%
85
Tax incentive2%
0
Climate / cooling2%
30

Nearby comparable sites

Other scored datacenter candidate sites in Poinsett County, ranked by DC Readiness.

Sites near Greenfield (INDEPENDENCE SUBSTATION - JONE)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN107738Substation-Adjacent161 kV100 MW1.4 yrs62.5
UNKNOWN107736Substation-Adjacent161 kV100 MW1.4 yrs62.5
TAP154804Substation-Adjacent161 kV100 MW1.4 yrs62.4
Greenfield (UNKNOWN107736 - TAP154804)Greenfield161 kV100 MW1.4 yrs56.0
Greenfield (UNKNOWN107736 - TAP154804)Greenfield161 kV100 MW1.4 yrs55.8
Greenfield (UNKNOWN107740 - UNKNOWN107997)Greenfield161 kV100 MW1.4 yrs52.9
Tyronza MuseumIndustrial43.2
Mine SiteFormer Mine42.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.