Datacenter Sites in Riverside County, California
Riverside County has 430 scored datacenter candidate sites averaging 44.5/100 DC Readiness, with a catalogued aggregate of 31,065 MW. FEMA rates local natural-hazard risk as "Relatively High".
430
Candidate sites
44.5/100
Avg DC Readiness
31,065 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Riverside County
No
Datacenter tax incentive
18.08¢/kWh
Commercial electricity
14.89¢/kWh
Industrial electricity
14
Fiber providers
High
Water stress
$19,831
Land price / acre
1,000
Cooling degree days
2,500
Heating degree days
59°F
Mean annual temp
By site type
Top datacenter sites in Riverside County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| RED BLUFF | Substation-Adjacent | 500 kV | 1,000 MW | 5.7 yrs | 63.9 |
| DEVERS | Substation-Adjacent | 500 kV | 1,000 MW | 5.7 yrs | 63.7 |
| UNKNOWN300795 | Substation-Adjacent | 230 kV | 300 MW | 5.7 yrs | 58.1 |
| BANNING | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 57.9 |
| JULIAN HINDS | Substation-Adjacent | 230 kV | 300 MW | 5.7 yrs | 57.7 |
| UNKNOWN307724 | Substation-Adjacent | 230 kV | 300 MW | 5.7 yrs | 57.0 |
| Greenfield (DEVERS - VALLEY) | Greenfield | 500 kV | 1,000 MW | 5.7 yrs | 56.9 |
| Greenfield (RED BLUFF - DEVERS) | Greenfield | 500 kV | 1,000 MW | 5.7 yrs | 56.7 |
| BANNING TAP | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 56.4 |
| TAP307979 | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 56.1 |
| VENWIND | Substation-Adjacent | 230 kV | 300 MW | 5.7 yrs | 55.9 |
| CONCHO | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 55.7 |
| TAP305309 | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 55.5 |
| Greenfield (RED BLUFF - DEVERS) | Greenfield | 500 kV | 1,000 MW | 5.7 yrs | 55.1 |
| TAMARISK | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 55.1 |
| EISENHOWER | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 55.0 |
| DESERT OUTPOST | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 54.9 |
| Greenfield (RED BLUFF - DEVERS) | Greenfield | 500 kV | 1,000 MW | 5.7 yrs | 54.6 |
| RENWIND | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 54.6 |
| JOSHUA TREE | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 54.5 |
| TAP302527 | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 54.3 |
| UNKNOWN303075 | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 54.2 |
| Greenfield (RED BLUFF - DEVERS) | Greenfield | 500 kV | 1,000 MW | 5.7 yrs | 54.1 |
| TRANSWIND | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 54.0 |
| COFFEE | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 54.0 |
Riverside County datacenter FAQ
- How many datacenter sites are in Riverside County?
- 430 scored datacenter candidate sites, averaging 44.5/100 DC Readiness.
- Does Riverside County offer datacenter tax incentives?
- No datacenter-specific tax incentive is on record for Riverside County in our dataset.
- What is the natural-hazard risk in Riverside County?
- FEMA's National Risk Index rates Riverside County as "Relatively High" (score 48).
- What are industrial electricity rates in Riverside County?
- Average industrial electricity is 14.89¢/kWh and commercial is 18.08¢/kWh in Riverside County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Riverside County, California. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.