Greenfield (None - None)

Greenfield

Ventura County, California · CAISO

DC Readiness
56.5
Good / 100

Greenfield (None - None) is a greenfield datacenter candidate site in Ventura County, California, interconnecting through CAISO. It screens at 56.5/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 5.7 yrs average interconnection-queue wait.

Power & interconnection

Substation voltage230 kV
Available capacity300 MW
LMP zoneCAISO_SP15
Wholesale LMP$11.23/MWh
Utility commercial rate0.18¢/kWh

Speed to power

ISO / RTO regionCAISO
Queue depth311
Avg queue wait5.7 yrs
Recent queue wait3.0 yrs
Completion rate11%
Withdrawal rate89%

Connectivity

Nearest IXPSD / Comsat Santa Paula Ground Station
IXP distance6.5 mi
Fiber providers12
Fiber coverage50.5%
Nearest cloud providerGCP
Nearest cloud regionus-west2
Cloud region distance55.7 mi

Site characteristics

Site typeGreenfield
Parcel ownerAZUSA LIGHT & POWER
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone X
Water stress (WRI)3.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score52/100
Construction cost index94.4 (avg 100)

Location context

Nearest datacenterSD / Comsat Santa Paula Ground Station
DC distance6.5 mi
Nearest rail3.0 mi
Nearest gas pipeline1.5 mi
Nearest fiber route94.6 mi
County hazard (FEMA NRI)Relatively High (48)
DC tax incentiveNo
Commercial electricity18.02¢/kWh
Industrial electricity14.52¢/kWh
Cooling degree days1,000
Heating degree days2,500
Land price / acre$28,278

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
35
Fiber connectivity12%
82
Energy cost10%
56
Water risk8%
49
Natural hazard8%
52
Buildability7%
80
Labor market4%
50
DC cluster4%
90
Land / acreage3%
30
Construction cost3%
71
Gas pipeline2%
95
Tax incentive2%
0
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Ventura County, ranked by DC Readiness.

Sites near Greenfield (None - None)
SiteTypeVoltageCapacityQueue waitScore
SANTA CLARASubstation-Adjacent230 kV300 MW5.7 yrs63.0
MISSIONSubstation-Adjacent230 kV300 MW5.7 yrs60.7
CASTAICSubstation-Adjacent230 kV300 MW5.7 yrs60.4
Greenfield (VINCENT - MIDWAY)Greenfield500 kV1,000 MW5.8 yrs60.2
Greenfield (VINCENT - MIDWAY)Greenfield500 kV1,000 MW5.8 yrs60.2
Greenfield (VINCENT - MIDWAY)Greenfield500 kV1,000 MW5.8 yrs60.2
Greenfield (MIDWAY - VINCENT)Greenfield500 kV1,000 MW5.8 yrs59.4
MESASubstation-Adjacent230 kV300 MW5.7 yrs59.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (None - None), Ventura County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.