Greenfield (MISSLE SITE - LIMON WIND #1)

Greenfield

Elbert County, Colorado · WECC

DC Readiness
61.7
Good / 100

Greenfield (MISSLE SITE - LIMON WIND #1) is a greenfield datacenter candidate site in Elbert County, Colorado, interconnecting through WECC. It screens at 61.7/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationMISSLE SITE
Substation voltage345 kV
Available capacity600 MW
Utility commercial rate0.13¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPEdgeConneX Denver (EDCDEN01)
IXP distance50.5 mi
Fiber providers11
Fiber coverage24.7%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance432.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerTriple R Farms Partnership Ltd Rlllp
Parcel APN7809400080
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone X
Water stress (WRI)3.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score75/100
Construction cost index82.7 (avg 100)

Location context

Nearest datacenterDatacenter 00916046040
DC distance48.3 mi
Nearest rail0.8 mi
Nearest gas pipeline8.2 mi
Nearest fiber route53.3 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.72¢/kWh
Industrial electricity8.77¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$2,935

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
33
Fiber connectivity12%
57
Energy cost10%
89
Water risk8%
58
Natural hazard8%
75
Buildability7%
80
Labor market4%
50
DC cluster4%
40
Land / acreage3%
51
Construction cost3%
81
Gas pipeline2%
74
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Elbert County, ranked by DC Readiness.

Sites near Greenfield (MISSLE SITE - LIMON WIND #1)
SiteTypeVoltageCapacityQueue waitScore
LIMON WIND #1Substation-Adjacent345 kV600 MW1.7 yrs64.6
CEDAR POINT WINDSubstation-Adjacent230 kV300 MW1.7 yrs62.7
CEDAR POINTSubstation-Adjacent230 kV300 MW1.7 yrs62.3
UNKNOWN204006Substation-Adjacent230 kV300 MW1.7 yrs62.0
Greenfield (MISSLE SITE - LIMON WIND #1)Greenfield345 kV600 MW1.7 yrs60.7
Greenfield (MISSLE SITE - LIMON WIND #1)Greenfield345 kV600 MW1.7 yrs60.6
Greenfield (MISSLE SITE - LIMON WIND #1)Greenfield345 kV600 MW1.7 yrs59.7
Greenfield (MISSLE SITE - UNKNOWN204006)Greenfield230 kV300 MW1.7 yrs58.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (MISSLE SITE - LIMON WIND #1), Elbert County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.