Greenfield (SHIPROCK - KAYENTA)

Greenfield

Montezuma County, Colorado · SPP

DC Readiness
59.2
Good / 100

Greenfield (SHIPROCK - KAYENTA) is a greenfield datacenter candidate site in Montezuma County, Colorado, interconnecting through SPP. It screens at 59.2/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationSHIPROCK
Substation voltage230 kV
Available capacity300 MW
LMP zoneSPP_SOUTH
Wholesale LMP$15.62/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth24
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Fiber providers8
Fiber coverage26.0%
Nearest cloud providerAzure
Nearest cloud regionwestus3
Cloud region distance295.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerNAVAJO TRIBAL UTILITY AUTHORITY
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub

Risk & environment

Flood zoneZone D
Water stress (WRI)3.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score75/100
Construction cost index59.3 (avg 100)

Location context

Nearest rail4.5 mi
Nearest gas pipeline3.0 mi
Nearest fiber route193.5 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.33¢/kWh
Industrial electricity8.28¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$1,736

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
47
Fiber connectivity12%
51
Energy cost10%
90
Water risk8%
44
Natural hazard8%
75
Buildability7%
70
Labor market4%
50
DC cluster4%
10
Land / acreage3%
53
Construction cost3%
100
Gas pipeline2%
91
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Montezuma County, ranked by DC Readiness.

Sites near Greenfield (SHIPROCK - KAYENTA)
SiteTypeVoltageCapacityQueue waitScore
LOST CANYONSubstation-Adjacent230 kV300 MW3.5 yrs65.1
Greenfield (PINTO - FOUR CORNERS)Greenfield345 kV600 MW3.5 yrs60.5
Greenfield (PINTO - FOUR CORNERS)Greenfield345 kV600 MW3.5 yrs60.2
Greenfield (PINTO - FOUR CORNERS)Greenfield345 kV600 MW3.5 yrs60.1
Greenfield (PINTO - FOUR CORNERS)Greenfield345 kV600 MW3.5 yrs60.0
Greenfield (PINTO - FOUR CORNERS)Greenfield345 kV600 MW3.5 yrs59.6
UNKNOWN301857Substation-Adjacent115 kV100 MW3.5 yrs59.4
Greenfield (PINTO - FOUR CORNERS)Greenfield345 kV600 MW3.5 yrs59.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (SHIPROCK - KAYENTA), Montezuma County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.