Datacenter Sites in Clay County, Florida
Clay County has 55 scored datacenter candidate sites averaging 61.4/100 DC Readiness, with a catalogued aggregate of 17,200 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
55
Candidate sites
61.4/100
Avg DC Readiness
17,200 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Clay County
Yessales_tax_exemption
Datacenter tax incentive
10.70¢/kWh
Commercial electricity
7.39¢/kWh
Industrial electricity
8
Fiber providers
Low-Medium
Water stress
$6,932
Land price / acre
3,500
Cooling degree days
700
Heating degree days
72°F
Mean annual temp
Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.
By site type
Top datacenter sites in Clay County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| SWITZERLAND | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 75.2 |
| SPRINGBANK | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 73.4 |
| Greenfield (DUVAL - RICE) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 71.4 |
| Greenfield (DUVAL - POINSETT) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 71.1 |
| FLEMING ISLAND | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 70.9 |
| DUVAL | Substation-Adjacent | 500 kV | 1,000 MW | 3.6 yrs | 70.2 |
| RICE | Substation-Adjacent | 500 kV | 1,000 MW | 3.6 yrs | 69.7 |
| Greenfield (DUVAL - POINSETT) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 69.2 |
| Greenfield (DUVAL - RICE) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 68.4 |
| Greenfield (DUVAL - POINSETT) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 68.1 |
| Greenfield (DUVAL - POINSETT) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 67.8 |
| LAKE ASBURY | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 67.6 |
| Greenfield (DUVAL - RICE) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 67.5 |
| KINGSLEY LAKE | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 67.4 |
| Greenfield (DUVAL - RICE) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 67.4 |
| Greenfield (BLACK CREEK - JAX HEIGHTS) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 67.1 |
| RUSSELL | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 67.1 |
| UNKNOWN120491 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 66.7 |
| BLACK CREEK | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 66.7 |
| TAP142924 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 66.1 |
| TAP142116 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 65.7 |
| Greenfield (RICE - BRADFORD) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 65.5 |
| Greenfield (UNKNOWN108250 - BLACK CREEK) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 65.4 |
| Greenfield (DUVAL - POINSETT) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 65.3 |
| TAP142922 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 65.1 |
Clay County datacenter FAQ
- How many datacenter sites are in Clay County?
- 55 scored datacenter candidate sites, averaging 61.4/100 DC Readiness.
- Does Clay County offer datacenter tax incentives?
- Sales tax exemption on manufacturing machinery including servers; no state income tax.
- What is the natural-hazard risk in Clay County?
- FEMA's National Risk Index rates Clay County as "Very High" (score 55).
- What are industrial electricity rates in Clay County?
- Average industrial electricity is 7.39¢/kWh and commercial is 10.70¢/kWh in Clay County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Clay County, Florida. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.