Datacenter Sites in Hardee, Florida
Hardee has 38 scored datacenter candidate sites averaging 57.3/100 DC Readiness, with a catalogued aggregate of 7,919 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
38
Candidate sites
57.3/100
Avg DC Readiness
7,919 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Hardee
Yessales_tax_exemption
Datacenter tax incentive
11.13¢/kWh
Commercial electricity
15.01¢/kWh
Industrial electricity
6
Fiber providers
Low-Medium
Water stress
$6,616
Land price / acre
3,500
Cooling degree days
700
Heating degree days
72°F
Mean annual temp
Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.
By site type
Top datacenter sites in Hardee
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| VANDOLAH POWER STATION | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 68.8 |
| MIDULLA GENERATING STATION | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 66.8 |
| Brownfield Site | Brownfield | — | 1,560 MW | 3.6 yrs | 66.2 |
| HARDEE POWER STATION | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 66.2 |
| UNKNOWN153224 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 65.8 |
| Polk | Brownfield | — | 1,859 MW | 3.6 yrs | 65.7 |
| UNKNOWN120311 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 65.3 |
| Greenfield (AVON PARK - FORT MEADE) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 64.9 |
| VANDOLAH | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 64.8 |
| EC Near Unknown | Greenfield | — | — | 3.6 yrs | 62.4 |
| EC Near Midulla Generating Station | Greenfield | — | — | 3.6 yrs | 61.9 |
| Greenfield (CHARLOTTE - VANDOLAH) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 61.9 |
| Greenfield (VANDOLAH - FORT MEADE) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 61.7 |
| EC Near Unknown | Greenfield | — | — | 3.6 yrs | 61.3 |
| EC Near Unknown | Greenfield | — | — | 3.6 yrs | 61.2 |
| Greenfield (VANDOLAH - FORT MEADE) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 60.6 |
| Greenfield (UNKNOWN120311 - HARDEE POWER S) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 60.3 |
| Greenfield (DESOTO NEXT GENERATION SOLAR E) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 58.6 |
| OZ Hardee | Greenfield | — | — | 3.6 yrs | 58.3 |
| Greenfield (DESOTO NEXT GENERATION SOLAR E) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 58.3 |
| Greenfield (VANDOLAH - WHIDDEN) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 58.2 |
| Greenfield (CHARLOTTE - VANDOLAH) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 57.5 |
| EC Near Unknown | Greenfield | — | — | 3.6 yrs | 57.2 |
| EC Near Midulla Generating Station | Greenfield | — | — | 3.6 yrs | 56.5 |
| EC Near Unknown | Greenfield | — | — | 3.6 yrs | 56.0 |
Hardee datacenter FAQ
- How many datacenter sites are in Hardee?
- 38 scored datacenter candidate sites, averaging 57.3/100 DC Readiness.
- Does Hardee offer datacenter tax incentives?
- Sales tax exemption on manufacturing machinery including servers; no state income tax.
- What is the natural-hazard risk in Hardee?
- FEMA's National Risk Index rates Hardee as "Very High" (score 55).
- What are industrial electricity rates in Hardee?
- Average industrial electricity is 15.01¢/kWh and commercial is 11.13¢/kWh in Hardee.
Dataset updated . Screening estimates derived from public data sources.