Datacenter Sites in Orange County, Florida
Orange County has 126 scored datacenter candidate sites averaging 61.3/100 DC Readiness, with a catalogued aggregate of 14,104 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
126
Candidate sites
61.3/100
Avg DC Readiness
14,104 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Orange County
Yessales_tax_exemption
Datacenter tax incentive
11.20¢/kWh
Commercial electricity
9.41¢/kWh
Industrial electricity
21
Fiber providers
Low-Medium
Water stress
$10,106
Land price / acre
3,500
Cooling degree days
700
Heating degree days
72°F
Mean annual temp
Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.
By site type
Top datacenter sites in Orange County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| DEADEND167102 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 76.0 |
| UNKNOWN120236 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 75.9 |
| WINDERMERE | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 75.9 |
| CONVENTION CENTER | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 75.8 |
| UNKNOWN120234 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 75.1 |
| TAFT | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 74.9 |
| INTERNATIONAL DRIVE | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 74.8 |
| STANTON | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 74.6 |
| PINE HILLS | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 74.1 |
| METROWEST | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 74.0 |
| RISER142185 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 73.5 |
| ALTAMONTE SPRINGS | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 73.5 |
| RISER143336 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 73.4 |
| PIEDMONT | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 73.4 |
| SOUTHWOOD | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 73.2 |
| UNKNOWN120225 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 71.9 |
| WOODSMERE | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 71.8 |
| RISER142188 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 71.4 |
| PERSHING | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 71.3 |
| CURRY FORD | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 71.0 |
| GRANT | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 71.0 |
| INTERCESSION CITY PLANT | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 70.8 |
| LAKE NONA | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 70.8 |
| RISER143335 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 70.6 |
| MICHIGAN | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 70.5 |
Orange County datacenter FAQ
- How many datacenter sites are in Orange County?
- 126 scored datacenter candidate sites, averaging 61.3/100 DC Readiness.
- Does Orange County offer datacenter tax incentives?
- Sales tax exemption on manufacturing machinery including servers; no state income tax.
- What is the natural-hazard risk in Orange County?
- FEMA's National Risk Index rates Orange County as "Very High" (score 55).
- What are industrial electricity rates in Orange County?
- Average industrial electricity is 9.41¢/kWh and commercial is 11.20¢/kWh in Orange County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Orange County, Florida. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.