Datacenter Sites in Union County, Florida
Union County has 11 scored datacenter candidate sites averaging 61.1/100 DC Readiness, with a catalogued aggregate of 1,300 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
11
Candidate sites
61.1/100
Avg DC Readiness
1,300 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Union County
Yessales_tax_exemption
Datacenter tax incentive
11.58¢/kWh
Commercial electricity
7.25¢/kWh
Industrial electricity
4
Fiber providers
Low-Medium
Water stress
$4,651
Land price / acre
3,500
Cooling degree days
700
Heating degree days
72°F
Mean annual temp
Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.
By site type
Top datacenter sites in Union County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN108496 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 66.4 |
| UNKNOWN108495 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 66.4 |
| UNKNOWN108265 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 64.9 |
| TAP142917 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 64.5 |
| Greenfield (DUVAL - RAVEN) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 60.0 |
| Greenfield (TAP161525 - DEADEND172575) | Greenfield | 115 kV | 100 MW | 3.6 yrs | 59.4 |
| LAKE BUTLER | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 59.2 |
| Greenfield (TAP161525 - DEADEND172575) | Greenfield | 115 kV | 100 MW | 3.6 yrs | 59.1 |
| PRICE | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 57.7 |
| Greenfield (UNKNOWN108265 - TAP142917) | Greenfield | 115 kV | 100 MW | 3.6 yrs | 57.6 |
| Greenfield (PRICE - LAKE BUTLER) | Greenfield | 115 kV | 100 MW | 3.6 yrs | 56.5 |
Union County datacenter FAQ
- How many datacenter sites are in Union County?
- 11 scored datacenter candidate sites, averaging 61.1/100 DC Readiness.
- Does Union County offer datacenter tax incentives?
- Sales tax exemption on manufacturing machinery including servers; no state income tax.
- What is the natural-hazard risk in Union County?
- FEMA's National Risk Index rates Union County as "Very High" (score 55).
- What are industrial electricity rates in Union County?
- Average industrial electricity is 7.25¢/kWh and commercial is 11.58¢/kWh in Union County.