Greenfield (UNKNOWN204860 - UNKNOWN205032)

Greenfield

Elmore County, Idaho · WECC

DC Readiness
64.0
Good / 100

Greenfield (UNKNOWN204860 - UNKNOWN205032) is a greenfield datacenter candidate site in Elmore County, Idaho, interconnecting through WECC. It screens at 64.0/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 2.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN204860
Substation voltage230 kV
Available capacity300 MW
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait2.0 yrs
Recent queue wait1.9 yrs
Completion rate30%
Withdrawal rate70%

Connectivity

Nearest IXPLevel(3) Boise
IXP distance22.7 mi
Fiber providers6
Fiber coverage31.0%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance270.4 mi

Site characteristics

Site typeGreenfield
Parcel ownerDitto Creek Ranch Llc
Parcel APNRP01S05E153640A
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone X
Water stress (WRI)2.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score85/100
Construction cost index68.6 (avg 100)

Location context

Nearest datacenterMeta Kuna Data Center
DC distance22.3 mi
Nearest rail5.9 mi
Nearest gas pipeline4.0 mi
Nearest fiber route28.9 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity8.92¢/kWh
Industrial electricity7.81¢/kWh
Cooling degree days500
Heating degree days6,400
Land price / acre$3,233

Incentive detail: Personal property tax exemption on computer equipment.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
42
Fiber connectivity12%
62
Energy cost10%
100
Water risk8%
44
Natural hazard8%
85
Buildability7%
80
Labor market4%
50
DC cluster4%
60
Land / acreage3%
50
Construction cost3%
93
Gas pipeline2%
87
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Elmore County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN204860 - UNKNOWN205032)
SiteTypeVoltageCapacityQueue waitScore
BENNETT MOUNTAINSubstation-Adjacent230 kV300 MW2.0 yrs71.9
EVANDER ANDREWS POWER COMPLEXSubstation-Adjacent230 kV300 MW2.0 yrs70.9
RYEGRASS WINDFARMSubstation-Adjacent230 kV300 MW2.0 yrs69.8
UNKNOWN205044Substation-Adjacent230 kV300 MW2.0 yrs69.5
COLD SPRINGS WINDFARMSubstation-Adjacent230 kV300 MW2.0 yrs68.5
HAMMETT HILL WINDFARMSubstation-Adjacent230 kV300 MW2.0 yrs68.3
MAINLINE WINDFARMSubstation-Adjacent230 kV300 MW2.0 yrs68.0
DESERT MEADOW WINDFARMSubstation-Adjacent230 kV300 MW2.0 yrs67.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.