Datacenter Sites in Teton County, Idaho
Teton County has 44 scored datacenter candidate sites averaging 49.7/100 DC Readiness, with a catalogued aggregate of 2,800 MW. FEMA rates local natural-hazard risk as "Relatively Low". The county has a datacenter tax incentive on record.
44
Candidate sites
49.7/100
Avg DC Readiness
2,800 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
Site-selection context for Teton County
Yesproperty_tax_exemption
Datacenter tax incentive
8.61¢/kWh
Commercial electricity
7.18¢/kWh
Industrial electricity
1
Fiber providers
Medium-High
Water stress
$5,512
Land price / acre
500
Cooling degree days
6,400
Heating degree days
44°F
Mean annual temp
Incentive detail: Personal property tax exemption on computer equipment.
By site type
Top datacenter sites in Teton County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| TAP206874 | Substation-Adjacent | 138 kV | 100 MW | 2.0 yrs | 63.9 |
| TAP204988 | Substation-Adjacent | 138 kV | 100 MW | 2.0 yrs | 63.6 |
| FELT | Substation-Adjacent | 138 kV | 100 MW | 2.0 yrs | 62.1 |
| TARGHEE TAP | Substation-Adjacent | 115 kV | 100 MW | 2.0 yrs | 61.6 |
| TETON | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 59.5 |
| CRYSTAL SPRINGS | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 59.3 |
| DRUMMOND | Substation-Adjacent | 161 kV | 100 MW | 2.0 yrs | 59.2 |
| UNKNOWN202286 | Substation-Adjacent | 161 kV | 100 MW | 1.7 yrs | 59.0 |
| TARGHEE | Substation-Adjacent | 115 kV | 100 MW | 2.0 yrs | 58.5 |
| EAST JACKSON 1&2 | Substation-Adjacent | 138 kV | 100 MW | 1.7 yrs | 58.0 |
| Greenfield (TARGHEE - DRUMMOND) | Greenfield | 115 kV | 100 MW | 2.0 yrs | 57.3 |
| Greenfield (TARGHEE - DRUMMOND) | Greenfield | 115 kV | 100 MW | 2.0 yrs | 57.1 |
| TARGHEE TAP | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 56.9 |
| Greenfield (TARGHEE - DRUMMOND) | Greenfield | 115 kV | 100 MW | 2.0 yrs | 56.7 |
| WILSON 1&2 | Substation-Adjacent | 161 kV | 100 MW | 1.7 yrs | 56.3 |
| VICTOR | Substation-Adjacent | 115 kV | 100 MW | 2.0 yrs | 55.6 |
| Greenfield (TARGHEE - DRUMMOND) | Greenfield | 115 kV | 100 MW | 2.0 yrs | 55.4 |
| UNKNOWN204381 | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 55.2 |
| UNKNOWN204382 | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 54.8 |
| RAFTER J | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 54.5 |
| Greenfield (TARGHEE TAP - TETON) | Greenfield | 115 kV | 100 MW | 1.7 yrs | 52.2 |
| Greenfield (SWAN VALLEY - TETON) | Greenfield | 115 kV | 100 MW | 1.7 yrs | 51.4 |
| Greenfield (SWAN VALLEY - TETON) | Greenfield | 115 kV | 100 MW | 1.7 yrs | 51.0 |
| Greenfield (SWAN VALLEY - TETON) | Greenfield | 115 kV | 100 MW | 1.7 yrs | 50.5 |
| Greenfield (UNKNOWN207237 - TAP207238) | Greenfield | 115 kV | 100 MW | 1.7 yrs | 50.3 |
Teton County datacenter FAQ
- How many datacenter sites are in Teton County?
- 44 scored datacenter candidate sites, averaging 49.7/100 DC Readiness.
- Does Teton County offer datacenter tax incentives?
- Personal property tax exemption on computer equipment.
- What is the natural-hazard risk in Teton County?
- FEMA's National Risk Index rates Teton County as "Relatively Low" (score 15).
- What are industrial electricity rates in Teton County?
- Average industrial electricity is 7.18¢/kWh and commercial is 8.61¢/kWh in Teton County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Teton County, Idaho. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.