UNKNOWN121886

Substation-Adjacent

Carroll, Illinois · MISO

DC Readiness
67.5
Good / 100

UNKNOWN121886 is a substation-adjacent datacenter candidate site in Carroll, Illinois, interconnecting through MISO. It screens at 67.5/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN121886
Substation distance0.0 mi
Substation voltage161 kV
Available capacity100 MW
LMP zoneMISO_MINN
Wholesale LMP$34.82/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth21
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPBluebird Quad Cities Data Center
IXP distance42.2 mi
Fiber providers4
Fiber coverage63.1%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance128.4 mi

Site characteristics

Parcel ownerCOMMONWEALTH EDISON CO
Land owner typeprivate
Buildability95.0/100
Land cover (NLCD)Developed, Medium Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteITC TRANSMISSION MIDWEST SAVANNA
Hazard sub-score55/100
Construction cost index66.9 (avg 100)

Location context

Nearest datacenterGeneseo Communications Inc
DC distance42.2 mi
Nearest rail0.6 mi
Nearest gas pipeline3.9 mi
Nearest fiber route39.8 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.58¢/kWh
Industrial electricity5.65¢/kWh
Cooling degree days1,100
Heating degree days5,600
Land price / acre$9,704

Incentive detail: Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
60
Speed to power15%
54
Fiber connectivity12%
67
Energy cost10%
85
Water risk8%
88
Natural hazard8%
55
Buildability7%
95
Labor market4%
50
DC cluster4%
45
Land / acreage3%
39
Construction cost3%
94
Gas pipeline2%
87
Tax incentive2%
100
Climate / cooling2%
70

Nearby comparable sites

Other scored datacenter candidate sites in Carroll, ranked by DC Readiness.

Sites near UNKNOWN121886
SiteTypeVoltageCapacityQueue waitScore
TAP137918Substation-Adjacent161 kV100 MW2.2 yrs68.2
TAP137918Substation-Adjacent161 kV100 MW1.4 yrs65.0
Greenfield (UNKNOWN121886 - UNKNOWN121920)Greenfield161 kV100 MW1.4 yrs60.9
EC FFE Carroll CountyGreenfield4.6 yrs60.7
Greenfield (UNKNOWN121886 - TAP137918)Greenfield161 kV100 MW2.2 yrs59.4
Greenfield (UNKNOWN122191 - TAP137918)Greenfield161 kV100 MW1.4 yrs59.2
OZ CarrollGreenfield4.6 yrs52.3
Thomson-40029Federal Excess42.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.