Greenfield (CASEY WEST - KANSAS WEST)

Greenfield

Cumberland County, Illinois · PJM

DC Readiness
64.1
Good / 100

Greenfield (CASEY WEST - KANSAS WEST) is a greenfield datacenter candidate site in Cumberland County, Illinois, interconnecting through PJM. It screens at 64.1/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 4.6 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationCASEY WEST
Substation voltage345 kV
Available capacity600 MW
LMP zonePJM_COMED
Wholesale LMP$33.95/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth265
Avg queue wait4.6 yrs
Recent queue wait2.9 yrs
Completion rate21%
Withdrawal rate79%

Connectivity

Nearest IXPIndiana University Data Center
IXP distance83.4 mi
Fiber providers5
Fiber coverage46.1%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance176.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerAMEREN ILLINOIS COMPANY
Land owner typeprivate
Buildability90.0/100
Land cover (NLCD)Developed, Open Space

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score65/100
Construction cost index112.1 (avg 100)

Location context

Nearest datacenterNCSA Petascale Computing Facility
DC distance52.7 mi
Nearest rail4.2 mi
Nearest gas pipeline22.3 mi
Nearest fiber route112.6 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.84¢/kWh
Industrial electricity7.66¢/kWh
Cooling degree days1,100
Heating degree days5,600
Land price / acre$8,894

Incentive detail: Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
44
Fiber connectivity12%
60
Energy cost10%
93
Water risk8%
88
Natural hazard8%
65
Buildability7%
90
Labor market4%
50
DC cluster4%
45
Land / acreage3%
41
Construction cost3%
57
Gas pipeline2%
28
Tax incentive2%
100
Climate / cooling2%
70

Nearby comparable sites

Other scored datacenter candidate sites in Cumberland County, ranked by DC Readiness.

Sites near Greenfield (CASEY WEST - KANSAS WEST)
SiteTypeVoltageCapacityQueue waitScore
NEOGASubstation-Adjacent345 kV600 MW4.6 yrs68.6
CASEY WESTSubstation-Adjacent345 kV600 MW4.6 yrs68.2
ENERGY SHELBY COUNTYSubstation-Adjacent138 kV100 MW4.6 yrs66.2
Greenfield (NEOGA - CASEY WEST)Greenfield345 kV600 MW4.6 yrs64.1
Greenfield (NEOGA - CASEY WEST)Greenfield345 kV600 MW4.6 yrs63.4
Greenfield (NEWTON STATION - CASEY WEST)Greenfield345 kV600 MW4.6 yrs63.1
EC FFE Cumberland CountyGreenfield4.6 yrs57.7
Greenfield (HUTSONVILLE - NEOGA)Greenfield138 kV100 MW4.6 yrs57.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.