Datacenter Sites in Kendall County, Illinois
Kendall County has 30 scored datacenter candidate sites averaging 65.0/100 DC Readiness, with a catalogued aggregate of 11,000 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
30
Candidate sites
65.0/100
Avg DC Readiness
11,000 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Kendall County
Yessales_tax_exemption
Datacenter tax incentive
9.48¢/kWh
Commercial electricity
4.94¢/kWh
Industrial electricity
4
Fiber providers
Low
Water stress
$11,745
Land price / acre
1,100
Cooling degree days
5,600
Heating degree days
52°F
Mean annual temp
Incentive detail: Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.
By site type
Top datacenter sites in Kendall County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| PLANO (765 KV) | Substation-Adjacent | 765 kV | 1,000 MW | 4.6 yrs | 78.7 |
| TAP138227 | Substation-Adjacent | 345 kV | 600 MW | 4.6 yrs | 74.4 |
| TAP138230 | Substation-Adjacent | 345 kV | 600 MW | 4.6 yrs | 74.3 |
| MONTGOMERY | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 71.6 |
| UNKNOWN121977 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 71.5 |
| PLANO (345 KV) | Substation-Adjacent | 345 kV | 600 MW | 4.6 yrs | 71.3 |
| TAP138242 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 70.8 |
| Greenfield (COLLINS - PLANO (765 KV)) | Greenfield | 765 kV | 1,000 MW | 4.6 yrs | 70.5 |
| Greenfield (COLLINS - PLANO (765 KV)) | Greenfield | 765 kV | 1,000 MW | 4.6 yrs | 69.7 |
| OSWEGO | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 68.9 |
| Greenfield (COLLINS - PLANO (765 KV)) | Greenfield | 765 kV | 1,000 MW | 4.6 yrs | 68.9 |
| Greenfield (COLLINS - PLANO (765 KV)) | Greenfield | 765 kV | 1,000 MW | 4.6 yrs | 68.8 |
| Greenfield (ELECTRIC LIGHT 345 KV - PLANO ) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 68.5 |
| PLANO (138 KV) | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 68.0 |
| TAP138226 | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 67.7 |
| UNKNOWN124334 | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 67.5 |
| TAP160102 | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 66.9 |
| UNKNOWN124332 | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 66.8 |
| UNKNOWN124334 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 66.6 |
| Greenfield (WOLFS CROSSING - DRESDEN STATI) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 66.3 |
| Greenfield (LA SALLE - PLANO (345 KV)) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 66.1 |
| Greenfield (TAP138233 - WOLFS CROSSING) | Greenfield | 138 kV | 100 MW | 2.2 yrs | 65.3 |
| Greenfield (LA SALLE - PLANO (345 KV)) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 65.0 |
| Greenfield (LA SALLE - PLANO (345 KV)) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 62.5 |
| Greenfield (UNKNOWN124333 - TAP138226) | Greenfield | 138 kV | 100 MW | 4.6 yrs | 62.1 |
Kendall County datacenter FAQ
- How many datacenter sites are in Kendall County?
- 30 scored datacenter candidate sites, averaging 65.0/100 DC Readiness.
- Does Kendall County offer datacenter tax incentives?
- Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.
- What is the natural-hazard risk in Kendall County?
- FEMA's National Risk Index rates Kendall County as "Relatively High" (score 35).
- What are industrial electricity rates in Kendall County?
- Average industrial electricity is 4.94¢/kWh and commercial is 9.48¢/kWh in Kendall County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Kendall County, Illinois. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.