Greenfield (SHAWNEE - WEST FRANKFORT EAST)

Greenfield

Massac County, Illinois · PJM

DC Readiness
69.0
Good / 100

Greenfield (SHAWNEE - WEST FRANKFORT EAST) is a greenfield datacenter candidate site in Massac County, Illinois, interconnecting through PJM. It screens at 69.0/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 4.6 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationSHAWNEE
Substation voltage345 kV
Available capacity600 MW
LMP zonePJM_COMED
Wholesale LMP$33.95/MWh
Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth265
Avg queue wait4.6 yrs
Recent queue wait2.9 yrs
Completion rate21%
Withdrawal rate79%

Connectivity

Nearest IXPQuad State Internet METRO1 Colocation
IXP distance11.2 mi
Fiber providers4
Fiber coverage100.0%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance322.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerAMEREN ILLINOIS COMPANY
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score65/100
Construction cost index72.7 (avg 100)

Location context

Nearest datacenterQuad State Internet METRO1 Colocation
DC distance11.2 mi
Nearest rail3.9 mi
Nearest gas pipeline6.0 mi
Nearest fiber route250.6 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.23¢/kWh
Industrial electricity5.09¢/kWh
Cooling degree days1,100
Heating degree days5,600
Land price / acre$4,582

Incentive detail: Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
44
Fiber connectivity12%
88
Energy cost10%
85
Water risk8%
88
Natural hazard8%
65
Buildability7%
70
Labor market4%
50
DC cluster4%
80
Land / acreage3%
48
Construction cost3%
89
Gas pipeline2%
81
Tax incentive2%
100
Climate / cooling2%
70

Nearby comparable sites

Other scored datacenter candidate sites in Massac County, ranked by DC Readiness.

Sites near Greenfield (SHAWNEE - WEST FRANKFORT EAST)
SiteTypeVoltageCapacityQueue waitScore
SHAWNEESubstation-Adjacent500 kV1,000 MW4.6 yrs81.3
JOPPA 345Substation-Adjacent345 kV600 MW4.6 yrs75.6
UNKNOWN121869Substation-Adjacent161 kV100 MW4.6 yrs70.4
Greenfield (SHAWNEE - WEST FRANKFORT EAST)Greenfield345 kV600 MW4.6 yrs69.1
Greenfield (JOPPA - WEST FRANKFORT)Greenfield230 kV300 MW4.6 yrs65.8
TAP153754Substation-Adjacent161 kV100 MW4.6 yrs64.4
TAP153782Substation-Adjacent161 kV100 MW4.6 yrs64.0
EC Coal Massac CountyGreenfield4.6 yrs63.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen