Datacenter Sites in Woodford County, Illinois
Woodford County has 26 scored datacenter candidate sites averaging 61.0/100 DC Readiness, with a catalogued aggregate of 9,700 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
26
Candidate sites
61.0/100
Avg DC Readiness
9,700 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Woodford County
Yessales_tax_exemption
Datacenter tax incentive
9.67¢/kWh
Commercial electricity
4.35¢/kWh
Industrial electricity
7
Fiber providers
Low
Water stress
$10,987
Land price / acre
1,100
Cooling degree days
5,600
Heating degree days
52°F
Mean annual temp
Incentive detail: Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.
By site type
Top datacenter sites in Woodford County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN122072 | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 68.4 |
| UNKNOWN160118 | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 67.5 |
| Greenfield (GOODINGS GROVE - POWERTON STAT) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 66.6 |
| Greenfield (TOP CROP - POWERTON STATION) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 66.6 |
| Greenfield (GOODINGS GROVE - POWERTON STAT) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 66.3 |
| Greenfield (TOP CROP - POWERTON STATION) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 66.2 |
| TAP138540 | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 66.1 |
| Greenfield (TAZEWELL - TAP138229) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 66.1 |
| MCLEAN WIND FARM STEP-UP TRANSFORMER | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 65.1 |
| Greenfield (TOP CROP - POWERTON STATION) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 65.1 |
| Greenfield (TAZEWELL - TAP138229) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 65.0 |
| Greenfield (TOP CROP - POWERTON STATION) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 64.9 |
| Greenfield (GOODINGS GROVE - POWERTON STAT) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 63.5 |
| Greenfield (UNKNOWN133789 - DRESDEN STATIO) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 63.3 |
| Greenfield (GOODINGS GROVE - POWERTON STAT) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 62.1 |
| Greenfield (TAZEWELL - TAP138229) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 61.8 |
| Greenfield (TAZEWELL - TAP138229) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 61.0 |
| Greenfield (UNKNOWN122071 - UNKNOWN160118) | Greenfield | 138 kV | 100 MW | 4.6 yrs | 60.9 |
| UNKNOWN123126 | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 60.2 |
| Greenfield (GOODINGS GROVE - POWERTON STAT) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 59.9 |
| Greenfield (TAZEWELL - TAP138229) | Greenfield | 345 kV | 600 MW | 4.6 yrs | 59.6 |
| Greenfield (UNKNOWN123126 - MCLEAN WIND FA) | Greenfield | 138 kV | 100 MW | 4.6 yrs | 59.4 |
| Mine Site | Former Mine | — | — | — | 45.5 |
| Mine Site | Former Mine | — | — | — | 45.4 |
| Mine Site | Former Mine | — | — | — | 45.4 |
Woodford County datacenter FAQ
- How many datacenter sites are in Woodford County?
- 26 scored datacenter candidate sites, averaging 61.0/100 DC Readiness.
- Does Woodford County offer datacenter tax incentives?
- Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.
- What is the natural-hazard risk in Woodford County?
- FEMA's National Risk Index rates Woodford County as "Relatively High" (score 35).
- What are industrial electricity rates in Woodford County?
- Average industrial electricity is 4.35¢/kWh and commercial is 9.67¢/kWh in Woodford County.
Dataset updated . Screening estimates derived from public data sources.