HARRISON, Indiana · PJM

DC Readiness
69.1
Good / 100

HE RAMSEY is a substation-adjacent datacenter candidate site in HARRISON, Indiana, interconnecting through PJM. It screens at 69.1/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationHE RAMSEY
Substation distance0.0 mi
Substation voltage345 kV
Available capacity600 MW
LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth56
Avg queue wait3.0 yrs
Recent queue wait4.2 yrs
Completion rate14%
Withdrawal rate87%

Connectivity

Nearest IXPHeyburn Building
IXP distance23.2 mi
Fiber providers2
Fiber coverage17.2%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance203.9 mi

Site characteristics

Parcel ownerDUKE ENERGY INDIANA INC
Land owner typeprivate
Buildability95.0/100
Land cover (NLCD)Developed, Medium Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatPresent
Superfund nearbyClear
Hazard sub-score48/100
Construction cost index60.6 (avg 100)

Location context

Nearest datacenterHeyburn Building
DC distance23.2 mi
Nearest rail1.1 mi
Nearest gas pipeline14.3 mi
Nearest fiber route110.4 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.07¢/kWh
Industrial electricity10.17¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$5,877

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
87
Speed to power15%
35
Fiber connectivity12%
59
Energy cost10%
83
Water risk8%
90
Natural hazard8%
48
Buildability7%
95
Labor market4%
50
DC cluster4%
60
Land / acreage3%
46
Construction cost3%
100
Gas pipeline2%
54
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in HARRISON, ranked by DC Readiness.

Sites near HE RAMSEY
SiteTypeVoltageCapacityQueue waitScore
TAP139013Substation-Adjacent345 kV600 MW3.0 yrs72.9
EC Coal Harrison CountyGreenfield3.0 yrs55.6
CHILD CRAFT INDUSTRIES, INC. (NONUPHOLSTERED WOOD HOUSEHOLD FURNITURE MANUFACTURING)Manufacturing51.6
SCHMIDT CABINET CO., INC. (WOOD KITCHEN CABINET AND COUNTERTOP MANUFACTURING)Manufacturing51.6
TYSON FOODS, INC. (POULTRY PROCESSING)Manufacturing51.5
ICON METAL FORMING, LLC (METAL STAMPING)Manufacturing51.4
LUCAS OIL PRODUCTS, INC. (NOT AVAILABLE)Manufacturing51.4
THORN-ORWICK (OTHER CONCRETE PRODUCT MANUFACTURING)Manufacturing51.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for HE RAMSEY, HARRISON. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.