LAGRANGE, Indiana · PJM

DC Readiness
61.2
Good / 100

LAGRANGE is a substation-adjacent datacenter candidate site in LAGRANGE, Indiana, interconnecting through PJM. It screens at 61.2/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationLAGRANGE
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.15¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth56
Avg queue wait3.0 yrs
Recent queue wait4.2 yrs
Completion rate14%
Withdrawal rate87%

Connectivity

Nearest IXPMidwest Energy & Communications
IXP distance32.9 mi
Fiber providers9
Fiber coverage99.6%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance111.3 mi

Site characteristics

Parcel ownerNORTHERN INDIANA PUB SERV CO
Land owner typeprivate
Buildability15.0/100
Land cover (NLCD)Woody Wetlands

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score68/100
Construction cost index79.0 (avg 100)

Location context

Nearest datacenterLagrange CO
DC distance5.0 mi
Nearest rail9.6 mi
Nearest gas pipeline3.7 mi
Nearest fiber route50.9 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity15.40¢/kWh
Industrial electricity7.48¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$14,455

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
35
Fiber connectivity12%
68
Energy cost10%
84
Water risk8%
90
Natural hazard8%
68
Buildability7%
15
Labor market4%
50
DC cluster4%
85
Land / acreage3%
31
Construction cost3%
84
Gas pipeline2%
88
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in LAGRANGE, ranked by DC Readiness.

Sites near LAGRANGE
SiteTypeVoltageCapacityQueue waitScore
Greenfield (HIPLE - ROBISON PARK (345 KV))Greenfield345 kV600 MW3.0 yrs63.9
Greenfield (UNKNOWN122933 - HIPLE)Greenfield138 kV100 MW3.0 yrs61.3
Greenfield (LAGRANGE - HIPLE)Greenfield138 kV100 MW3.0 yrs56.8
Greenfield (LAGRANGE - HIPLE)Greenfield138 kV100 MW3.0 yrs56.3
Greenfield (LAGRANGE - UNKNOWN123174)Greenfield138 kV100 MW3.0 yrs54.7
DEUTSCHE KASE HAUS, INC. (CHEESE MANUFACTURING)Manufacturing52.5
RIEGSECKER HARDWOODS (WOOD KITCHEN CABINET AND COUNTERTOP MANUFACTURING)Manufacturing52.4
FORKS RV, INC. (TRUCK TRAILER MANUFACTURING)Manufacturing52.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for LAGRANGE, LAGRANGE. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.