EC Near Centerville

Greenfield

Appanoose, Iowa · MISO

DC Readiness
59.1
Good / 100

EC Near Centerville is a greenfield datacenter candidate site in Appanoose, Iowa, interconnecting through MISO. It screens at 59.1/100 DC Readiness and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneMISO_MINN
Wholesale LMP$34.82/MWh
Utility commercial rate0.13¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth21
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPConnect Des Moines
IXP distance67.3 mi
Fiber providers9
Fiber coverage66.4%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance75.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerMIDAMERICAN ENERGY CO
Land owner typeprivate
Buildability75.0/100
Land cover (NLCD)Pasture/Hay
Former usenear retired oil plant (5km)

Risk & environment

Flood zoneZone A (SFHA)
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score55/100
Construction cost index91.1 (avg 100)

Location context

Nearest datacenterDatacenter 944024849
DC distance62.9 mi
Nearest rail0.8 mi
Nearest gas pipeline2.3 mi
Nearest fiber route33.0 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.42¢/kWh
Industrial electricity8.19¢/kWh
Cooling degree days900
Heating degree days6,500
Land price / acre$4,927

Incentive detail: Sales tax exemption on DC equipment for $1M+ investments; property tax phase-in for new construction.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
55
Fiber connectivity12%
64
Energy cost10%
84
Water risk8%
87
Natural hazard8%
55
Buildability7%
75
Labor market4%
50
DC cluster4%
30
Land / acreage3%
47
Construction cost3%
74
Gas pipeline2%
93
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Appanoose, ranked by DC Readiness.

Sites near EC Near Centerville
SiteTypeVoltageCapacityQueue waitScore
APPANOOSESubstation-Adjacent161 kV100 MW1.4 yrs67.0
EC Near CentervilleGreenfield1.4 yrs61.2
CentervilleBrownfield60 MW1.4 yrs61.0
EC Near CentervilleGreenfield1.4 yrs60.6
EC Near CentervilleGreenfield1.4 yrs60.6
EC Near CentervilleGreenfield1.4 yrs60.3
Greenfield (UNKNOWN117964 - APPANOOSE)Greenfield161 kV100 MW1.4 yrs60.1
EC Near CentervilleGreenfield1.4 yrs59.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Near Centerville, Appanoose. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.