UNKNOWN118098

Substation-Adjacent

Leavenworth County, Kansas · SPP

DC Readiness
64.3
Good / 100

UNKNOWN118098 is a substation-adjacent datacenter candidate site in Leavenworth County, Kansas, interconnecting through SPP. It screens at 64.3/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN118098
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth16
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPLightEdge Kansas City Cavern (KCI2)
IXP distance23.0 mi
Fiber providers6
Fiber coverage100.0%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance154.8 mi

Site characteristics

Parcel ownerWESTAR ENERGY INC
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)2.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score65/100
Construction cost index80.1 (avg 100)

Location context

Nearest datacenterState Farm Data Center
DC distance19.6 mi
Nearest rail4.8 mi
Nearest gas pipeline1.1 mi
Nearest fiber route24.6 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity11.14¢/kWh
Industrial electricity9.44¢/kWh
Cooling degree days1,400
Heating degree days5,000
Land price / acre$5,077

Incentive detail: PEAK program payroll tax incentives; IRB property tax exemptions available.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
51
Fiber connectivity12%
77
Energy cost10%
90
Water risk8%
67
Natural hazard8%
65
Buildability7%
45
Labor market4%
50
DC cluster4%
65
Land / acreage3%
47
Construction cost3%
83
Gas pipeline2%
97
Tax incentive2%
100
Climate / cooling2%
55

Nearby comparable sites

Other scored datacenter candidate sites in Leavenworth County, ranked by DC Readiness.

Sites near UNKNOWN118098
SiteTypeVoltageCapacityQueue waitScore
STRANGER CREEKSubstation-Adjacent345 kV600 MW3.5 yrs69.8
UNKNOWN118854Substation-Adjacent115 kV100 MW3.5 yrs69.6
UNKNOWN118853Substation-Adjacent115 kV100 MW3.5 yrs69.5
UNKNOWN118099Substation-Adjacent115 kV100 MW3.5 yrs67.8
Greenfield (UNKNOWN118616 - STRANGER CREEK)Greenfield345 kV600 MW3.5 yrs66.1
UNKNOWN117986Substation-Adjacent115 kV100 MW3.5 yrs66.0
Greenfield (HOYT - STRANGER CREEK)Greenfield345 kV600 MW3.5 yrs65.7
UNKNOWN118776Substation-Adjacent115 kV100 MW3.5 yrs65.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN118098, Leavenworth County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.