UNKNOWN125673

Substation-Adjacent

Boyle, Kentucky · PJM

DC Readiness
66.5
Good / 100

UNKNOWN125673 is a substation-adjacent datacenter candidate site in Boyle, Kentucky, interconnecting through PJM. It screens at 66.5/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.6 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN125673
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth221
Avg queue wait3.6 yrs
Recent queue wait4.7 yrs
Completion rate7%
Withdrawal rate93%

Connectivity

Nearest IXPQX.Net Lexington
IXP distance31.4 mi
Fiber providers2
Fiber coverage56.8%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance186.2 mi

Site characteristics

Parcel ownerKentucky Utilities Company
Land owner typeprivate
Buildability100.0/100
Land cover (NLCD)Developed, High Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteBOB ALLEN PONTIAC CADILLAC GMC NISSAN IN
Hazard sub-score60/100
Construction cost index68.9 (avg 100)

Location context

Nearest datacenterQX.Net Lexington
DC distance31.4 mi
Nearest rail0.7 mi
Nearest gas pipeline1.3 mi
Nearest fiber route100.4 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.99¢/kWh
Industrial electricity7.30¢/kWh
Cooling degree days1,300
Heating degree days4,300
Land price / acre$5,423

Incentive detail: Sales tax exemption on electricity for large industrial users; KBI tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
37
Fiber connectivity12%
64
Energy cost10%
93
Water risk8%
87
Natural hazard8%
60
Buildability7%
100
Labor market4%
50
DC cluster4%
45
Land / acreage3%
62
Construction cost3%
93
Gas pipeline2%
96
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Boyle, ranked by DC Readiness.

Sites near UNKNOWN125673
SiteTypeVoltageCapacityQueue waitScore
EC Coal Boyle CountyGreenfield3.6 yrs60.0
EC FFE Boyle CountyGreenfield3.6 yrs58.3
OZ BoyleGreenfield3.6 yrs57.4
Greenfield (UNKNOWN124683 - TAP155537)Greenfield138 kV100 MW3.6 yrs52.4
John H. Stigall Business CenterShovel-Ready49.0
Davco Industrial SiteShovel-Ready49.0
Norfolk Southern-- Site 021-005Shovel-Ready48.9
John Hill Bailey Industrial Park Enterprise CenterShovel-Ready48.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN125673, Boyle. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.