West Industrial Park

Shovel-Ready

Logan County, Kentucky · PJM

DC Readiness
58.1
Good / 100

West Industrial Park is a shovel-ready datacenter candidate site in Logan County, Kentucky, interconnecting through PJM. It screens at 58.1/100 DC Readiness.

Power & interconnection

Speed to power

ISO / RTO regionPJM
Queue depth221

Connectivity

Nearest IXPRussellvile EPB Smartnet
IXP distance2.2 mi

Site characteristics

Site typeShovel-Ready
Acreage167 ac
Former useShovel-ready

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score70/100

Location context

Nearest datacenterRussellvile EPB Smartnet
DC distance2.2 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.55¢/kWh
Industrial electricity6.13¢/kWh
Cooling degree days1,300
Heating degree days4,300
Land price / acre$6,404

Incentive detail: Sales tax exemption on electricity for large industrial users; KBI tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
50
Fiber connectivity12%
87
Energy cost10%
50
Water risk8%
92
Natural hazard8%
70
Buildability7%
50
Labor market4%
50
DC cluster4%
100
Land / acreage3%
60
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Logan County, ranked by DC Readiness.

Sites near West Industrial Park
SiteTypeVoltageCapacityQueue waitScore
RUSSELLVILLESubstation-Adjacent161 kV100 MW3.6 yrs72.8
LOGAN ALUMINUMSubstation-Adjacent161 kV100 MW3.6 yrs70.3
LEWISBURGSubstation-Adjacent161 kV100 MW3.6 yrs68.1
Greenfield (PARADISE - TAP155146)Greenfield161 kV100 MW3.7 yrs67.7
Greenfield (PARADISE - TAP155146)Greenfield161 kV100 MW3.7 yrs67.5
LOST CITYSubstation-Adjacent161 kV100 MW3.6 yrs66.8
Greenfield (PARADISE - TAP155146)Greenfield161 kV100 MW3.7 yrs66.4
Greenfield (ADAIRVILLE - TAP153493)Greenfield161 kV100 MW3.7 yrs66.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for West Industrial Park, Logan County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.