North Hamilton Street Brownfield Project

Industrial

Scott County, Kentucky · PJM

DC Readiness
46.4
Fair / 100

North Hamilton Street Brownfield Project is a industrial datacenter candidate site in Scott County, Kentucky, interconnecting through PJM. It screens at 46.4/100 DC Readiness.

Power & interconnection

Speed to power

ISO / RTO regionPJM
Queue depth221

Connectivity

Nearest IXPQX.Net Lexington
IXP distance12.2 mi

Site characteristics

Site typeIndustrial

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score50/100

Location context

Nearest datacenterQX.Net Lexington
DC distance12.2 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.29¢/kWh
Industrial electricity6.81¢/kWh
Cooling degree days1,300
Heating degree days4,300
Land price / acre$6,387

Incentive detail: Sales tax exemption on electricity for large industrial users; KBI tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
52
Fiber connectivity12%
58
Energy cost10%
50
Water risk8%
50
Natural hazard8%
50
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
43
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
0
Climate / cooling2%
50

Nearby comparable sites

Other scored datacenter candidate sites in Scott County, ranked by DC Readiness.

Sites near North Hamilton Street Brownfield Project
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN129128Substation-Adjacent138 kV100 MW3.6 yrs69.6
UNKNOWN129119Substation-Adjacent138 kV100 MW3.0 yrs67.7
UNKNOWN129127Substation-Adjacent138 kV100 MW3.6 yrs67.6
UNKNOWN129119Substation-Adjacent138 kV100 MW3.6 yrs67.6
UNKNOWN129115Substation-Adjacent138 kV100 MW3.0 yrs66.9
UNKNOWN129115Substation-Adjacent138 kV100 MW3.6 yrs66.6
Greenfield (UNKNOWN129119 - HAEFLING)Greenfield138 kV100 MW3.6 yrs62.7
Greenfield (GHENT STATION - UNKNOWN155025)Greenfield138 kV100 MW3.0 yrs60.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for North Hamilton Street Brownfield Project, Scott County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.