Greenfield (BARKLEY - DOVER)

Greenfield

Trigg County, Kentucky · PJM

DC Readiness
57.0
Good / 100

Greenfield (BARKLEY - DOVER) is a greenfield datacenter candidate site in Trigg County, Kentucky, interconnecting through PJM. It screens at 57.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 4.6 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationBARKLEY
Substation voltage161 kV
Available capacity100 MW
LMP zonePJM_COMED
Wholesale LMP$33.95/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth265
Avg queue wait4.6 yrs
Recent queue wait2.9 yrs
Completion rate21%
Withdrawal rate79%

Connectivity

Nearest IXPEnergynet Datacenter
IXP distance31.4 mi
Fiber providers2
Fiber coverage69.2%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance350.8 mi

Site characteristics

Site typeGreenfield
Parcel ownerTENNESSEE VALLEY AUTHORITY
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score70/100
Construction cost index51.4 (avg 100)

Location context

Nearest datacenterEnergynet Datacenter
DC distance31.4 mi
Nearest rail15.1 mi
Nearest gas pipeline5.1 mi
Nearest fiber route193.5 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.03¢/kWh
Industrial electricity4.97¢/kWh
Cooling degree days1,300
Heating degree days4,300
Land price / acre$5,078

Incentive detail: Sales tax exemption on electricity for large industrial users; KBI tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
32
Speed to power15%
43
Fiber connectivity12%
55
Energy cost10%
85
Water risk8%
92
Natural hazard8%
70
Buildability7%
45
Labor market4%
50
DC cluster4%
40
Land / acreage3%
47
Construction cost3%
100
Gas pipeline2%
84
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Trigg County, ranked by DC Readiness.

Sites near Greenfield (BARKLEY - DOVER)
SiteTypeVoltageCapacityQueue waitScore
CADIZSubstation-Adjacent161 kV100 MW4.6 yrs67.5
Greenfield (CADIZ - TAP156043)Greenfield161 kV100 MW4.6 yrs60.7
Greenfield (BARKLEY - DOVER)Greenfield161 kV100 MW4.6 yrs57.5
Greenfield (BARKLEY - DOVER)Greenfield161 kV100 MW4.6 yrs57.0
EC Coal Trigg CountyGreenfield3.6 yrs54.9
Interstate 24 Business ParkShovel-Ready52.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (BARKLEY - DOVER), Trigg County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.