Datacenter Sites in Iberville Parish, Louisiana
Iberville Parish has 39 scored datacenter candidate sites averaging 58.9/100 DC Readiness, with a catalogued aggregate of 5,965 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
39
Candidate sites
58.9/100
Avg DC Readiness
5,965 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Iberville Parish
Yessales_tax_exemption
Datacenter tax incentive
12.97¢/kWh
Commercial electricity
9.94¢/kWh
Industrial electricity
7
Fiber providers
Low
Water stress
$2,562
Land price / acre
2,700
Cooling degree days
1,700
Heating degree days
67°F
Mean annual temp
Incentive detail: Industrial Tax Exemption Program (ITEP) up to 80% property tax abatement for 10 years.
By site type
Top datacenter sites in Iberville Parish
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN149836 | Substation-Adjacent | 500 kV | 1,000 MW | 1.4 yrs | 72.9 |
| LaO Energy Systems | Brownfield | — | 715 MW | — | 71.8 |
| PLAQUEMINE COGENERATION PLANT | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 71.2 |
| UNKNOWN112489 | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 70.8 |
| PLAQUEMINE | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 69.2 |
| UNKNOWN115494 | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 69.0 |
| UNKNOWN115492 | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 68.2 |
| UNKNOWN112500 | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 65.9 |
| UNKNOWN115462 | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 64.0 |
| UNKNOWN112493 | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 63.9 |
| UNKNOWN112496 | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 63.1 |
| Greenfield (UNKNOWN149836 - WEBRE) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 62.2 |
| Greenfield (UNKNOWN112496 - UNKNOWN112500) | Greenfield | 230 kV | 300 MW | 1.4 yrs | 61.9 |
| EC Near Willow Glen | Greenfield | — | — | 1.4 yrs | 60.5 |
| EC Near Willow Glen | Greenfield | — | — | 1.4 yrs | 60.3 |
| Plaquemine | Brownfield | — | 44 MW | 1.4 yrs | 59.7 |
| EC Near Plaquemine | Greenfield | — | — | 1.4 yrs | 59.5 |
| EC Near PCS Nitrogen Fertilizer LP | Greenfield | — | — | 1.4 yrs | 59.4 |
| EC Near PCS Nitrogen Fertilizer LP | Greenfield | — | — | 1.4 yrs | 59.0 |
| EC Near PCS Nitrogen Fertilizer LP | Greenfield | — | — | 1.4 yrs | 58.8 |
| EC Near PCS Nitrogen Fertilizer LP | Greenfield | — | — | 1.4 yrs | 58.5 |
| EC Near Willow Glen | Greenfield | — | — | 1.4 yrs | 56.6 |
| OZ Iberville | Greenfield | — | — | 1.4 yrs | 56.5 |
| EC Near Willow Glen | Greenfield | — | — | 1.4 yrs | 56.2 |
| EC Near LaO Energy Systems | Greenfield | — | — | 1.4 yrs | 55.8 |
Iberville Parish datacenter FAQ
- How many datacenter sites are in Iberville Parish?
- 39 scored datacenter candidate sites, averaging 58.9/100 DC Readiness.
- Does Iberville Parish offer datacenter tax incentives?
- Industrial Tax Exemption Program (ITEP) up to 80% property tax abatement for 10 years.
- What is the natural-hazard risk in Iberville Parish?
- FEMA's National Risk Index rates Iberville Parish as "Very High" (score 58).
- What are industrial electricity rates in Iberville Parish?
- Average industrial electricity is 9.94¢/kWh and commercial is 12.97¢/kWh in Iberville Parish.
Dataset updated . Screening estimates derived from public data sources.