Greenfield (UNKNOWN123228 - UNKNOWN123242)

Greenfield

Dorchester, Maryland · PJM

DC Readiness
61.7
Good / 100

Greenfield (UNKNOWN123228 - UNKNOWN123242) is a greenfield datacenter candidate site in Dorchester, Maryland, interconnecting through PJM. It screens at 61.7/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.1 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN123228
Substation voltage230 kV
Available capacity300 MW
LMP zonePJM_DOM
Wholesale LMP$43.92/MWh
Utility commercial rate0.14¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth864
Avg queue wait3.1 yrs
Recent queue wait3.6 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPAiNET MD-790R
IXP distance59.1 mi
Fiber providers3
Fiber coverage11.3%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance96.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerDELMARVA POWER
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone X
Water stress (WRI)0.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score78/100
Construction cost index70.4 (avg 100)

Location context

Nearest datacenterCyberNAP Glen Burnie
DC distance59.2 mi
Nearest rail6.3 mi
Nearest gas pipeline7.8 mi
Nearest fiber route3.1 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (property_tax_credits)
Commercial electricity13.58¢/kWh
Industrial electricity11.29¢/kWh
Cooling degree days1,300
Heating degree days4,400
Land price / acre$7,614

Incentive detail: Enterprise Zone property tax credits; personal property tax credits on DC equipment.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
39
Fiber connectivity12%
51
Energy cost10%
95
Water risk8%
87
Natural hazard8%
78
Buildability7%
65
Labor market4%
50
DC cluster4%
45
Land / acreage3%
43
Construction cost3%
91
Gas pipeline2%
75
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Dorchester, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN123228 - UNKNOWN123242)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN123242Substation-Adjacent230 kV300 MW3.1 yrs67.9
OZ DorchesterGreenfield3.5 yrs53.7
OZ DorchesterGreenfield3.5 yrs50.5
Phillips PackagingIndustrial41.7
Mine SiteFormer Mine36.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN123228 - UNKNOWN123242), Dorchester. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.