Montgomery, Maryland · PJM

DC Readiness
75.6
Excellent / 100

TAP139321 is a substation-adjacent datacenter candidate site in Montgomery, Maryland, interconnecting through PJM. It screens at 75.6/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 3.1 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP139321
Substation distance0.0 mi
Substation voltage500 kV
Available capacity1,000 MW
LMP zonePJM_DOM
Wholesale LMP$43.92/MWh
Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth864
Avg queue wait3.1 yrs
Recent queue wait3.6 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPAtlantech Online - Rockville, MD
IXP distance16.2 mi
Fiber providers13
Fiber coverage96.7%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance24.5 mi

Site characteristics

Parcel ownerTHE POTOMAC EDISON COMPANY
Land owner typeprivate
Buildability60.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)0.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score78/100
Construction cost index110.2 (avg 100)

Location context

Nearest datacenterDatacenter 00178331621
DC distance13.9 mi
Nearest rail4.5 mi
Nearest gas pipeline5.5 mi
Nearest fiber route7.6 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (property_tax_credits)
Commercial electricity9.80¢/kWh
Industrial electricity11.09¢/kWh
Cooling degree days1,300
Heating degree days4,400
Land price / acre$10,739

Incentive detail: Enterprise Zone property tax credits; personal property tax credits on DC equipment.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
100
Speed to power15%
39
Fiber connectivity12%
84
Energy cost10%
83
Water risk8%
88
Natural hazard8%
78
Buildability7%
60
Labor market4%
50
DC cluster4%
95
Land / acreage3%
52
Construction cost3%
58
Gas pipeline2%
82
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Montgomery, ranked by DC Readiness.

Sites near TAP139321
SiteTypeVoltageCapacityQueue waitScore
CLARKSBURGSubstation-Adjacent230 kV300 MW3.1 yrs74.8
NORBECKSubstation-Adjacent230 kV300 MW3.1 yrs73.7
UNKNOWN122905Substation-Adjacent230 kV300 MW3.1 yrs73.6
BELLS MILLSubstation-Adjacent230 kV300 MW3.1 yrs72.5
QUINCE ORCHARDSubstation-Adjacent230 kV300 MW3.1 yrs71.0
DICKERSONSubstation-Adjacent230 kV300 MW3.1 yrs67.3
Greenfield (QUINCE ORCHARD - BELLS MILL)Greenfield230 kV300 MW3.1 yrs66.5
MOUNT ZIONSubstation-Adjacent230 kV300 MW3.1 yrs65.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.