Datacenter Sites in Eaton County, Michigan
Eaton County has 79 scored datacenter candidate sites averaging 52.6/100 DC Readiness, with a catalogued aggregate of 5,700 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
79
Candidate sites
52.6/100
Avg DC Readiness
5,700 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Eaton County
Yesproperty_tax_exemption
Datacenter tax incentive
12.17¢/kWh
Commercial electricity
6.73¢/kWh
Industrial electricity
12
Fiber providers
Low
Water stress
$5,160
Land price / acre
700
Cooling degree days
6,600
Heating degree days
45°F
Mean annual temp
Incentive detail: Personal property tax exemption for eligible DC equipment; MEGA tax credits.
By site type
Top datacenter sites in Eaton County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN156787 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 74.3 |
| UNKNOWN128596 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 73.2 |
| UNKNOWN156624 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 71.1 |
| UNKNOWN128591 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 70.6 |
| ONEIDA | Substation-Adjacent | 345 kV | 600 MW | 2.2 yrs | 69.8 |
| Greenfield (MAJESTIC - ONEIDA) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 69.7 |
| Greenfield (BATTLE CREEK - ONEIDA) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 67.9 |
| EC Coal Eaton County | Greenfield | — | — | 2.2 yrs | 67.2 |
| Greenfield (MAJESTIC - ONEIDA) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 67.2 |
| EC Near Erickson Station | Greenfield | — | — | 2.2 yrs | 66.1 |
| OZ Eaton | Greenfield | — | — | 2.2 yrs | 65.8 |
| Greenfield (MAJESTIC - ONEIDA) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 65.1 |
| UNKNOWN128696 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 64.7 |
| Greenfield (MAJESTIC - ONEIDA) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 64.6 |
| EC Near Erickson Station | Greenfield | — | — | 2.2 yrs | 63.3 |
| Greenfield (TOMPKINS - ARGENTA) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 63.3 |
| EC Near Erickson Station | Greenfield | — | — | 2.2 yrs | 63.3 |
| Greenfield (ISLAND ROAD - TAP156312) | Greenfield | 138 kV | 100 MW | 2.2 yrs | 63.2 |
| TAP140110 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 63.2 |
| Greenfield (UNKNOWN128696 - TAP140110) | Greenfield | 138 kV | 100 MW | 2.2 yrs | 63.0 |
| Greenfield (TOMPKINS - ARGENTA) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 62.7 |
| ISLAND ROAD | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 62.3 |
| EC Near Erickson Station | Greenfield | — | — | 2.2 yrs | 62.2 |
| EC Coal Eaton County | Greenfield | — | — | 2.2 yrs | 61.9 |
| EC Coal Eaton County | Greenfield | — | — | 2.2 yrs | 60.9 |
Eaton County datacenter FAQ
- How many datacenter sites are in Eaton County?
- 79 scored datacenter candidate sites, averaging 52.6/100 DC Readiness.
- Does Eaton County offer datacenter tax incentives?
- Personal property tax exemption for eligible DC equipment; MEGA tax credits.
- What is the natural-hazard risk in Eaton County?
- FEMA's National Risk Index rates Eaton County as "Relatively Moderate" (score 25).
- What are industrial electricity rates in Eaton County?
- Average industrial electricity is 6.73¢/kWh and commercial is 12.17¢/kWh in Eaton County.
Dataset updated . Screening estimates derived from public data sources.