EC FFE Gratiot County

Greenfield

Gratiot County, Michigan · PJM

DC Readiness
63.3
Good / 100

EC FFE Gratiot County is a greenfield datacenter candidate site in Gratiot County, Michigan, interconnecting through PJM. It screens at 63.3/100 DC Readiness and a 2.2 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_ATSI
Wholesale LMP$42.97/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth11
Avg queue wait2.2 yrs
Recent queue wait2.2 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPLiquid Web DC3
IXP distance40.7 mi
Fiber providers10
Fiber coverage50.4%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance182.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerCONSUMERS ENERGY CO
Land owner typeprivate
Buildability95.0/100
Land cover (NLCD)Developed, Medium Intensity
Former usefossil fuel employment

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteGRATIOT COUNTY COURT HOUSE
Hazard sub-score65/100
Construction cost index60.3 (avg 100)

Location context

Nearest datacenterLiquid Web, Inc
DC distance40.7 mi
Nearest rail0.3 mi
Nearest gas pipeline1.9 mi
Nearest fiber route179.1 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity11.74¢/kWh
Industrial electricity6.33¢/kWh
Cooling degree days700
Heating degree days6,600
Land price / acre$6,512

Incentive detail: Personal property tax exemption for eligible DC equipment; MEGA tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
56
Fiber connectivity12%
64
Energy cost10%
81
Water risk8%
94
Natural hazard8%
65
Buildability7%
95
Labor market4%
50
DC cluster4%
45
Land / acreage3%
45
Construction cost3%
100
Gas pipeline2%
94
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Gratiot County, ranked by DC Readiness.

Sites near EC FFE Gratiot County
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN128569Substation-Adjacent345 kV600 MW2.2 yrs74.9
RENAISSANCE STATIONSubstation-Adjacent345 kV600 MW2.2 yrs74.9
TAP145748Substation-Adjacent138 kV100 MW2.2 yrs69.5
TAP145655Substation-Adjacent138 kV100 MW2.2 yrs69.0
Greenfield (UNKNOWN128569 - UNKNOWN128625)Greenfield345 kV600 MW2.2 yrs67.8
VESTABURGSubstation-Adjacent138 kV100 MW2.2 yrs67.5
UNKNOWN128546Substation-Adjacent138 kV100 MW2.2 yrs67.2
TAP140108Substation-Adjacent138 kV100 MW2.2 yrs66.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.