Datacenter Sites in Otsego County, Michigan
Otsego County has 31 scored datacenter candidate sites averaging 60.0/100 DC Readiness, with a catalogued aggregate of 3,800 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
31
Candidate sites
60.0/100
Avg DC Readiness
3,800 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Otsego County
Yesproperty_tax_exemption
Datacenter tax incentive
12.19¢/kWh
Commercial electricity
7.79¢/kWh
Industrial electricity
9
Fiber providers
Low
Water stress
$3,545
Land price / acre
700
Cooling degree days
6,600
Heating degree days
45°F
Mean annual temp
Incentive detail: Personal property tax exemption for eligible DC equipment; MEGA tax credits.
By site type
Top datacenter sites in Otsego County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| LIVINGSTON | Substation-Adjacent | 345 kV | 600 MW | 2.2 yrs | 73.3 |
| LIVINGSTON GENERATING STATION | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 68.5 |
| GAYLORD - CONSUMERS | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 68.0 |
| UNKNOWN133923 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 67.7 |
| UNKNOWN128860 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 67.4 |
| GAYLORD - WOLVERINE | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 67.1 |
| Greenfield (LIVINGSTON - GALLAGHER) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 67.0 |
| Greenfield (LIVINGSTON - KEYSTONE) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 66.8 |
| VAN TYLE | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 66.5 |
| UNKNOWN143794 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 65.7 |
| Greenfield (LIVINGSTON - GALLAGHER) | Greenfield | 345 kV | 600 MW | 2.2 yrs | 63.8 |
| UNKNOWN128880 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 62.3 |
| UNKNOWN143793 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 62.2 |
| UNKNOWN143809 | Substation-Adjacent | 138 kV | 100 MW | 2.2 yrs | 61.4 |
| EC Near Gaylord - Consumers | Greenfield | — | — | 2.2 yrs | 60.5 |
| EC Near Gaylord - Consumers | Greenfield | — | — | 2.2 yrs | 60.1 |
| Greenfield (GAYLORD - WOLVERINE - UNKNOWN1) | Greenfield | 138 kV | 100 MW | 2.2 yrs | 60.1 |
| EC Near Gaylord - Consumers | Greenfield | — | — | 2.2 yrs | 59.3 |
| Greenfield (UNKNOWN128860 - LIVINGSTON) | Greenfield | 138 kV | 100 MW | 2.2 yrs | 58.9 |
| Greenfield (GAYLORD - WOLVERINE - UNKNOWN1) | Greenfield | 138 kV | 100 MW | 2.2 yrs | 58.7 |
| Greenfield (TAP143808 - TAP143810) | Greenfield | 138 kV | 100 MW | 2.2 yrs | 58.6 |
| EC Near Gaylord - Consumers | Greenfield | — | — | 2.2 yrs | 58.5 |
| EC Near Gaylord - Consumers | Greenfield | — | — | 2.2 yrs | 58.4 |
| EC Near Gaylord - Consumers | Greenfield | — | — | 2.2 yrs | 57.9 |
| EC Near Gaylord - Consumers | Greenfield | — | — | 2.2 yrs | 57.9 |
Otsego County datacenter FAQ
- How many datacenter sites are in Otsego County?
- 31 scored datacenter candidate sites, averaging 60.0/100 DC Readiness.
- Does Otsego County offer datacenter tax incentives?
- Personal property tax exemption for eligible DC equipment; MEGA tax credits.
- What is the natural-hazard risk in Otsego County?
- FEMA's National Risk Index rates Otsego County as "Relatively Moderate" (score 25).
- What are industrial electricity rates in Otsego County?
- Average industrial electricity is 7.79¢/kWh and commercial is 12.19¢/kWh in Otsego County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Otsego County, Michigan. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.