Greenfield (TAP135615 - RIVERTON 115/34 KV)

Greenfield

Aitkin County, Minnesota · MISO

DC Readiness
53.0
Fair / 100

Greenfield (TAP135615 - RIVERTON 115/34 KV) is a greenfield datacenter candidate site in Aitkin County, Minnesota, interconnecting through MISO. It screens at 53.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP135615
Substation voltage115 kV
Available capacity100 MW
LMP zoneMISO_MINN
Wholesale LMP$34.82/MWh
Utility commercial rate0.14¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth16
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPark data centers - Duluth, MN
IXP distance77.5 mi
Fiber providers8
Fiber coverage65.9%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance343.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerMINNESOTA POWER INC
Land owner typeprivate
Buildability50.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score65/100
Construction cost index65.3 (avg 100)

Location context

Nearest datacenterArk Duluth Data Center
DC distance77.5 mi
Nearest rail6.4 mi
Nearest gas pipeline26.2 mi
Nearest fiber route124.0 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.87¢/kWh
Industrial electricity9.39¢/kWh
Cooling degree days600
Heating degree days7,700
Land price / acre$2,854

Incentive detail: Sales tax exemption on DC equipment and electricity for qualified DCs.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power15%
57
Fiber connectivity12%
24
Energy cost10%
87
Water risk8%
90
Natural hazard8%
65
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
51
Construction cost3%
96
Gas pipeline2%
16
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Aitkin County, ranked by DC Readiness.

Sites near Greenfield (TAP135615 - RIVERTON 115/34 KV)
SiteTypeVoltageCapacityQueue waitScore
Greenfield (UNKNOWN133416 - ARROWHEAD)Greenfield250 kV300 MW1.4 yrs66.6
UNKNOWN130769Substation-Adjacent115 kV100 MW1.4 yrs66.5
Greenfield (BLACKBERRY - RIVERTON 230/115 )Greenfield230 kV300 MW1.4 yrs66.3
UNKNOWN129688Substation-Adjacent115 kV100 MW1.4 yrs65.6
Greenfield (UNKNOWN133416 - ARROWHEAD)Greenfield250 kV300 MW1.4 yrs63.8
Greenfield (BLACKBERRY - RIVERTON 230/115 )Greenfield230 kV300 MW1.4 yrs63.7
UNKNOWN130767Substation-Adjacent115 kV100 MW1.4 yrs63.7
Greenfield (UNKNOWN133416 - ARROWHEAD)Greenfield250 kV300 MW1.4 yrs63.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (TAP135615 - RIVERTON 115/34 KV), Aitkin County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.