AMITE, Mississippi · MISO

DC Readiness
68.9
Good / 100

FRANKLIN is a substation-adjacent datacenter candidate site in AMITE, Mississippi, interconnecting through MISO. It screens at 68.9/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationFRANKLIN
Substation distance0.0 mi
Substation voltage500 kV
Available capacity1,000 MW
LMP zoneMISO_LOUISIANA
Wholesale LMP$32.39/MWh
Utility commercial rate0.14¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth176
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPVenyu BTR1
IXP distance68.7 mi
Fiber providers1
Fiber coverage2.7%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance372.2 mi

Site characteristics

Parcel ownerENTERGY MISSISSIPPI INC
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score55/100
Construction cost index58.7 (avg 100)

Location context

Nearest datacenterVenyu BTR1
DC distance68.7 mi
Nearest rail10.1 mi
Nearest gas pipeline12.5 mi
Nearest fiber route79.4 mi
County hazard (FEMA NRI)Relatively High (45)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.95¢/kWh
Industrial electricity8.62¢/kWh
Cooling degree days2,400
Heating degree days2,400
Land price / acre$3,315

Incentive detail: Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
100
Speed to power15%
54
Fiber connectivity12%
42
Energy cost10%
88
Water risk8%
90
Natural hazard8%
55
Buildability7%
70
Labor market4%
50
DC cluster4%
20
Land / acreage3%
50
Construction cost3%
100
Gas pipeline2%
60
Tax incentive2%
100
Climate / cooling2%
5

Nearby comparable sites

Other scored datacenter candidate sites in AMITE, ranked by DC Readiness.

Sites near FRANKLIN
SiteTypeVoltageCapacityQueue waitScore
Greenfield (MC KNIGHT - FRANKLIN)Greenfield500 kV1,000 MW1.4 yrs64.3
Greenfield (MC KNIGHT - FRANKLIN)Greenfield500 kV1,000 MW1.4 yrs63.8
UNKNOWN110657Substation-Adjacent115 kV100 MW1.4 yrs62.3
Greenfield (MC KNIGHT - FRANKLIN)Greenfield500 kV1,000 MW1.4 yrs61.4
UNKNOWN110652Substation-Adjacent115 kV100 MW1.4 yrs60.4
Greenfield (MC KNIGHT - FRANKLIN)Greenfield500 kV1,000 MW1.4 yrs59.0
TAP142946Substation-Adjacent115 kV100 MW1.4 yrs58.9
Greenfield (UNKNOWN110653 - UNKNOWN110657)Greenfield115 kV100 MW1.4 yrs55.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.