Datacenter Sites in Coahoma County, Mississippi
Coahoma County has 55 scored datacenter candidate sites averaging 52.0/100 DC Readiness, with a catalogued aggregate of 1,700 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
55
Candidate sites
52.0/100
Avg DC Readiness
1,700 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Coahoma County
Yessales_tax_exemption
Datacenter tax incentive
11.12¢/kWh
Commercial electricity
6.98¢/kWh
Industrial electricity
5
Fiber providers
Low
Water stress
$3,910
Land price / acre
2,400
Cooling degree days
2,400
Heating degree days
64°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.
By site type
Top datacenter sites in Coahoma County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| CROSSROADS ENERGY CENTER | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 67.0 |
| UNKNOWN111259 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 64.5 |
| TAP150099 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 64.3 |
| UNKNOWN111252 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 63.9 |
| TAP150100 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 62.9 |
| UNKNOWN111253 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 62.9 |
| Greenfield (CROSSROADS ENERGY CENTER - UNK) | Greenfield | 230 kV | 300 MW | 1.4 yrs | 62.7 |
| UNKNOWN111254 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 62.2 |
| UNKNOWN107730 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 61.4 |
| EC FFE Coahoma County | Greenfield | — | — | 1.4 yrs | 61.0 |
| EC Near Third Street | Greenfield | — | — | 1.4 yrs | 60.8 |
| TAP150096 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 60.7 |
| UNKNOWN110736 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 60.7 |
| EC Near Third Street | Greenfield | — | — | 1.4 yrs | 59.1 |
| EC Near Third Street | Greenfield | — | — | 1.4 yrs | 59.1 |
| EC Near Third Street | Greenfield | — | — | 1.4 yrs | 58.6 |
| EC Near Third Street | Greenfield | — | — | 1.4 yrs | 58.4 |
| EC Near Third Street | Greenfield | — | — | 1.4 yrs | 58.2 |
| EC Near Third Street | Greenfield | — | — | 1.4 yrs | 57.9 |
| OZ Coahoma | Greenfield | — | — | 1.4 yrs | 57.3 |
| EC Near Third Street | Greenfield | — | — | 1.4 yrs | 56.5 |
| Greenfield (UNKNOWN111252 - TAP150096) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 55.8 |
| EC Near Third Street | Greenfield | — | — | 1.4 yrs | 55.8 |
| EC Near Third Street | Greenfield | — | — | 1.4 yrs | 54.3 |
| TAP149957 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 52.2 |
Coahoma County datacenter FAQ
- How many datacenter sites are in Coahoma County?
- 55 scored datacenter candidate sites, averaging 52.0/100 DC Readiness.
- Does Coahoma County offer datacenter tax incentives?
- Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.
- What is the natural-hazard risk in Coahoma County?
- FEMA's National Risk Index rates Coahoma County as "Relatively High" (score 45).
- What are industrial electricity rates in Coahoma County?
- Average industrial electricity is 6.98¢/kWh and commercial is 11.12¢/kWh in Coahoma County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Coahoma County, Mississippi. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.