EC Coal Monroe County

Greenfield

Monroe County, Mississippi · MISO

DC Readiness
52.5
Fair / 100

EC Coal Monroe County is a greenfield datacenter candidate site in Monroe County, Mississippi, interconnecting through MISO. It screens at 52.5/100 DC Readiness and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneMISO_MS
Wholesale LMP$31.68/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth13
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPC Spire Mississippi
IXP distance36.9 mi
Fiber providers7
Fiber coverage79.5%
Nearest cloud providerGCP
Nearest cloud regionus-east1
Cloud region distance483.8 mi

Site characteristics

Site typeGreenfield
Parcel ownerRenfro Thomas Eugene
Parcel APN3210-01-000-001.00
Land owner typeprivate
Buildability40.0/100
Land cover (NLCD)Evergreen Forest
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score55/100
Construction cost index88.1 (avg 100)

Location context

Nearest datacenterC Spire Mississippi
DC distance36.9 mi
Nearest rail2.3 mi
Nearest gas pipeline2.7 mi
Nearest fiber route65.1 mi
County hazard (FEMA NRI)Relatively High (45)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.23¢/kWh
Industrial electricity6.07¢/kWh
Cooling degree days2,400
Heating degree days2,400
Land price / acre$2,359

Incentive detail: Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
59
Fiber connectivity12%
28
Energy cost10%
85
Water risk8%
90
Natural hazard8%
55
Buildability7%
40
Labor market4%
50
DC cluster4%
40
Land / acreage3%
52
Construction cost3%
77
Gas pipeline2%
91
Tax incentive2%
100
Climate / cooling2%
5

Nearby comparable sites

Other scored datacenter candidate sites in Monroe County, ranked by DC Readiness.

Sites near EC Coal Monroe County
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN109811Substation-Adjacent161 kV100 MW1.4 yrs67.9
UNKNOWN109621Substation-Adjacent161 kV100 MW1.4 yrs67.6
Greenfield (WESTPOINT - BROWNS FERRY)Greenfield500 kV1,000 MW1.4 yrs66.9
UNKNOWN109595Substation-Adjacent161 kV100 MW1.4 yrs66.8
Greenfield (WESTPOINT - LOWNDES)Greenfield500 kV1,000 MW1.4 yrs66.8
Greenfield (WESTPOINT - BROWNS FERRY)Greenfield500 kV1,000 MW1.4 yrs66.5
UNKNOWN109821Substation-Adjacent161 kV100 MW1.4 yrs65.8
UNKNOWN109813Substation-Adjacent161 kV100 MW1.4 yrs65.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Coal Monroe County, Monroe County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.