Datacenter Sites in Iron County, Missouri
Iron County has 10 scored datacenter candidate sites averaging 50.7/100 DC Readiness, with a catalogued aggregate of 700 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
10
Candidate sites
50.7/100
Avg DC Readiness
700 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Iron County
Yessales_tax_exemption
Datacenter tax incentive
10.91¢/kWh
Commercial electricity
7.38¢/kWh
Industrial electricity
2
Fiber providers
Low
Water stress
$2,697
Land price / acre
1,500
Cooling degree days
4,700
Heating degree days
56°F
Mean annual temp
Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.
By site type
Top datacenter sites in Iron County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN117877 | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 58.8 |
| TAUM SAUK | Substation-Adjacent | 138 kV | 100 MW | 4.6 yrs | 58.3 |
| Greenfield (UNKNOWN117877 - TAP153691) | Greenfield | 138 kV | 100 MW | 4.6 yrs | 54.6 |
| Greenfield (TAUM SAUK - RIVERMINE) | Greenfield | 138 kV | 100 MW | 4.6 yrs | 54.6 |
| Greenfield (UNKNOWN117781 - TAP153228) | Greenfield | 138 kV | 100 MW | 4.6 yrs | 54.3 |
| Greenfield (UNKNOWN117877 - TAP153691) | Greenfield | 138 kV | 100 MW | 4.6 yrs | 53.8 |
| Greenfield (TAUM SAUK - RIVERMINE) | Greenfield | 138 kV | 100 MW | 4.6 yrs | 52.8 |
| Mine Site | Former Mine | — | — | — | 41.6 |
| Mine Site | Former Mine | — | — | — | 41.3 |
| Mine Site | Former Mine | — | — | — | 36.9 |
Iron County datacenter FAQ
- How many datacenter sites are in Iron County?
- 10 scored datacenter candidate sites, averaging 50.7/100 DC Readiness.
- Does Iron County offer datacenter tax incentives?
- Qualified data center sales tax exemption (2019 law); state income tax credits.
- What is the natural-hazard risk in Iron County?
- FEMA's National Risk Index rates Iron County as "Relatively High" (score 38).
- What are industrial electricity rates in Iron County?
- Average industrial electricity is 7.38¢/kWh and commercial is 10.91¢/kWh in Iron County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Iron County, Missouri. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.