Greenfield (UNKNOWN206281 - TAP208247)

Greenfield

Toole County, Montana · SPP

DC Readiness
59.0
Good / 100

Greenfield (UNKNOWN206281 - TAP208247) is a greenfield datacenter candidate site in Toole County, Montana, interconnecting through SPP. It screens at 59.0/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 1.1 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN206281
Substation voltage230 kV
Available capacity300 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh

Speed to power

ISO / RTO regionSPP
Queue depth1
Avg queue wait1.1 yrs
Recent queue wait0.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Fiber providers2
Fiber coverage42.4%
Nearest cloud providerAzure
Nearest cloud regionwestus2
Cloud region distance372.8 mi

Site characteristics

Site typeGreenfield
Parcel ownerMcalpine Ranches Inc
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone X
Water stress (WRI)2.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score88/100
Construction cost index86.6 (avg 100)

Location context

Nearest rail11.4 mi
Nearest gas pipeline8.5 mi
Nearest fiber route172.0 mi
County hazard (FEMA NRI)Very Low (12)
DC tax incentiveYes (property_tax_abatement)
Cooling degree days400
Heating degree days7,600
Land price / acre$1,287

Incentive detail: New/expanding industry tax abatement available for DC construction.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
74
Fiber connectivity12%
18
Energy cost10%
83
Water risk8%
50
Natural hazard8%
88
Buildability7%
65
Labor market4%
50
DC cluster4%
10
Land / acreage3%
54
Construction cost3%
78
Gas pipeline2%
73
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Toole County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN206281 - TAP208247)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN206280Substation-Adjacent230 kV300 MW1.1 yrs72.1
SHELBYSubstation-Adjacent230 kV300 MW1.1 yrs71.4
UNKNOWN206279Substation-Adjacent230 kV300 MW1.1 yrs69.8
UNKNOWN206281Substation-Adjacent230 kV300 MW1.1 yrs69.1
NATURENER RIM ROCK ENERGYSubstation-Adjacent230 kV300 MW1.1 yrs68.0
TAP204145Substation-Adjacent115 kV100 MW1.1 yrs68.0
Greenfield (CONRAD - SHELBY)Greenfield230 kV300 MW1.1 yrs66.7
NATURENER GLACIER WIND ENERGY 1Substation-Adjacent115 kV100 MW1.1 yrs66.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen