Toole County, Montana · SPP

DC Readiness
65.5
Good / 100

TAP204146 is a substation-adjacent datacenter candidate site in Toole County, Montana, interconnecting through SPP. It screens at 65.5/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.1 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP204146
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh

Speed to power

ISO / RTO regionSPP
Queue depth1
Avg queue wait1.1 yrs
Recent queue wait0.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPiConnect Missoula
IXP distance143.6 mi
Fiber providers2
Fiber coverage42.4%
Nearest cloud providerAzure
Nearest cloud regionwestus2
Cloud region distance361.8 mi

Site characteristics

Parcel ownerNorthwestern Corporation
Land owner typeprivate
Buildability60.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)2.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteCUT BANK STATION GLACIER PIPELINE
Hazard sub-score78/100
Construction cost index86.6 (avg 100)

Location context

Nearest datacenteriConnect Missoula
DC distance143.6 mi
Nearest rail1.0 mi
Nearest gas pipeline8.5 mi
Nearest fiber route147.5 mi
County hazard (FEMA NRI)Very Low (12)
DC tax incentiveYes (property_tax_abatement)
Cooling degree days400
Heating degree days7,600
Land price / acre$1,287

Incentive detail: New/expanding industry tax abatement available for DC construction.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
74
Fiber connectivity12%
60
Energy cost10%
83
Water risk8%
57
Natural hazard8%
78
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
69
Construction cost3%
78
Gas pipeline2%
73
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Toole County, ranked by DC Readiness.

Sites near TAP204146
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN206280Substation-Adjacent230 kV300 MW1.1 yrs72.1
SHELBYSubstation-Adjacent230 kV300 MW1.1 yrs71.4
UNKNOWN206279Substation-Adjacent230 kV300 MW1.1 yrs69.8
UNKNOWN206281Substation-Adjacent230 kV300 MW1.1 yrs69.1
NATURENER RIM ROCK ENERGYSubstation-Adjacent230 kV300 MW1.1 yrs68.0
TAP204145Substation-Adjacent115 kV100 MW1.1 yrs68.0
Greenfield (CONRAD - SHELBY)Greenfield230 kV300 MW1.1 yrs66.7
NATURENER GLACIER WIND ENERGY 1Substation-Adjacent115 kV100 MW1.1 yrs66.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP204146, Toole County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.