Greenfield (UNKNOWN131937 - COLUMBUS EAST)

Greenfield

Butler County, Nebraska · SPP

DC Readiness
61.7
Good / 100

Greenfield (UNKNOWN131937 - COLUMBUS EAST) is a greenfield datacenter candidate site in Butler County, Nebraska, interconnecting through SPP. It screens at 61.7/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN131937
Substation voltage345 kV
Available capacity600 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth31
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPBinary Net Vault
IXP distance35.3 mi
Fiber providers6
Fiber coverage44.1%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance73.8 mi

Site characteristics

Site typeGreenfield
Parcel ownerLOUP RIVER PUBLIC POWER DIST
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone X
Water stress (WRI)2.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score72/100
Construction cost index86.3 (avg 100)

Location context

Nearest datacenterLincoln Data Centers
DC distance35.3 mi
Nearest rail3.8 mi
Nearest gas pipeline6.8 mi
Nearest fiber route55.0 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.03¢/kWh
Industrial electricity8.23¢/kWh
Cooling degree days1,000
Heating degree days6,200
Land price / acre$6,462

Incentive detail: ImagiNE Nebraska Act: sales tax exemption on DC equipment; investment tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
39
Fiber connectivity12%
60
Energy cost10%
91
Water risk8%
60
Natural hazard8%
72
Buildability7%
65
Labor market4%
50
DC cluster4%
50
Land / acreage3%
45
Construction cost3%
78
Gas pipeline2%
78
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Butler County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN131937 - COLUMBUS EAST)
SiteTypeVoltageCapacityQueue waitScore
COLUMBUS EASTSubstation-Adjacent345 kV600 MW3.5 yrs69.9
Greenfield (UNKNOWN131937 - COLUMBUS EAST)Greenfield345 kV600 MW3.5 yrs64.4
UNKNOWN131890Substation-Adjacent115 kV100 MW3.5 yrs61.9
Greenfield (UNKNOWN131937 - COLUMBUS EAST)Greenfield345 kV600 MW3.5 yrs61.9
Greenfield (UNKNOWN131937 - COLUMBUS EAST)Greenfield345 kV600 MW3.5 yrs60.9
Greenfield (UNKNOWN131890 - UNKNOWN131892)Greenfield115 kV100 MW3.5 yrs58.6
Greenfield (UNKNOWN131890 - COLUMBUS EAST)Greenfield115 kV100 MW3.5 yrs58.0
Greenfield (UNKNOWN131843 - UNKNOWN131882)Greenfield115 kV100 MW3.5 yrs57.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.