EC Near Cambridge

Greenfield

Furnas, Nebraska · SPP

DC Readiness
56.9
Good / 100

EC Near Cambridge is a greenfield datacenter candidate site in Furnas, Nebraska, interconnecting through SPP. It screens at 56.9/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh

Speed to power

ISO / RTO regionSPP
Queue depth31
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPBeloit-NOC
IXP distance121.8 mi
Fiber providers6
Fiber coverage63.8%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance230.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerNEBRASKA PUBLIC POWER DISTRICT
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops
Former usenear retired oil plant (10km)

Risk & environment

Flood zoneZone X
Water stress (WRI)2.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score72/100
Construction cost index86.3 (avg 100)

Location context

Nearest datacenterCompute North
DC distance61.2 mi
Nearest rail3.8 mi
Nearest gas pipeline1.9 mi
Nearest fiber route169.3 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Cooling degree days1,000
Heating degree days6,200
Land price / acre$2,895

Incentive detail: ImagiNE Nebraska Act: sales tax exemption on DC equipment; investment tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
39
Fiber connectivity12%
65
Energy cost10%
84
Water risk8%
72
Natural hazard8%
72
Buildability7%
65
Labor market4%
50
DC cluster4%
40
Land / acreage3%
51
Construction cost3%
78
Gas pipeline2%
94
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Furnas, ranked by DC Readiness.

Sites near EC Near Cambridge
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN131958Substation-Adjacent115 kV100 MW3.5 yrs63.6
EC Near CambridgeGreenfield3.5 yrs57.5
EC Near CambridgeGreenfield3.5 yrs57.4
EC Near CambridgeGreenfield3.5 yrs56.4
EC Near CambridgeGreenfield3.5 yrs56.4
EC Near CambridgeGreenfield3.5 yrs56.3
EC Near CambridgeGreenfield3.5 yrs55.2
EC Near CambridgeGreenfield3.5 yrs55.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.