Greenfield (JOHNSON 2 - UNKNOWN131961)

Greenfield

Gosper County, Nebraska · SPP

DC Readiness
54.9
Fair / 100

Greenfield (JOHNSON 2 - UNKNOWN131961) is a greenfield datacenter candidate site in Gosper County, Nebraska, interconnecting through SPP. It screens at 54.9/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationJOHNSON 2
Substation voltage115 kV
Available capacity100 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth31
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPBeloit-NOC
IXP distance116.2 mi
Fiber providers4
Fiber coverage34.2%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance205.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerDAWSON POWER DISTRICT
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone X
Water stress (WRI)2.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score72/100
Construction cost index86.3 (avg 100)

Location context

Nearest datacenterCompute North
DC distance35.4 mi
Nearest rail4.1 mi
Nearest gas pipeline1.3 mi
Nearest fiber route154.2 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity8.66¢/kWh
Industrial electricity10.48¢/kWh
Cooling degree days1,000
Heating degree days6,200
Land price / acre$4,514

Incentive detail: ImagiNE Nebraska Act: sales tax exemption on DC equipment; investment tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power15%
39
Fiber connectivity12%
55
Energy cost10%
91
Water risk8%
60
Natural hazard8%
72
Buildability7%
65
Labor market4%
50
DC cluster4%
40
Land / acreage3%
48
Construction cost3%
78
Gas pipeline2%
96
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Gosper County, ranked by DC Readiness.

Sites near Greenfield (JOHNSON 2 - UNKNOWN131961)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN131959Substation-Adjacent115 kV100 MW3.5 yrs61.7
UNKNOWN131768Substation-Adjacent115 kV100 MW3.5 yrs60.0
JOHNSON 2Substation-Adjacent115 kV100 MW3.5 yrs57.6
Greenfield (JOHNSON 2 - UNKNOWN131959)Greenfield115 kV100 MW3.5 yrs57.1
Greenfield (JOHNSON 2 - UNKNOWN131959)Greenfield115 kV100 MW3.5 yrs56.3
Greenfield (JOHNSON 2 - UNKNOWN131961)Greenfield115 kV100 MW3.5 yrs56.1
Greenfield (UNKNOWN131958 - UNKNOWN131959)Greenfield115 kV100 MW3.5 yrs55.8
Greenfield (JOHNSON 2 - UNKNOWN131961)Greenfield115 kV100 MW3.5 yrs54.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (JOHNSON 2 - UNKNOWN131961), Gosper County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.