Greenfield (UNKNOWN132856 - FORT RANDALL)

Greenfield

Knox County, Nebraska · SPP

DC Readiness
62.9
Good / 100

Greenfield (UNKNOWN132856 - FORT RANDALL) is a greenfield datacenter candidate site in Knox County, Nebraska, interconnecting through SPP. It screens at 62.9/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN132856
Substation voltage230 kV
Available capacity300 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.07¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth17
Avg queue wait1.0 yrs
Recent queue wait0.6 yrs
Completion rate22%
Withdrawal rate78%

Connectivity

Nearest IXPMidco Yankton
IXP distance45.3 mi
Fiber providers6
Fiber coverage55.0%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance143.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerWAPA-- WESTERN AREA POWER ADMINISTRATION
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous

Risk & environment

Flood zoneZone X
Water stress (WRI)2.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score72/100
Construction cost index54.6 (avg 100)

Location context

Nearest datacenterMidco Yankton
DC distance45.3 mi
Nearest rail10.2 mi
Nearest gas pipeline19.6 mi
Nearest fiber route39.7 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity7.02¢/kWh
Industrial electricity13.44¢/kWh
Cooling degree days1,000
Heating degree days6,200
Land price / acre$5,161

Incentive detail: ImagiNE Nebraska Act: sales tax exemption on DC equipment; investment tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
53
Fiber connectivity12%
59
Energy cost10%
88
Water risk8%
66
Natural hazard8%
72
Buildability7%
80
Labor market4%
50
DC cluster4%
45
Land / acreage3%
47
Construction cost3%
100
Gas pipeline2%
37
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Knox County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN132856 - FORT RANDALL)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN132471Substation-Adjacent115 kV100 MW1.0 yrs66.6
Greenfield (UNKNOWN131929 - FORT THOMPSON)Greenfield345 kV600 MW1.0 yrs64.7
Greenfield (UNKNOWN131929 - FORT THOMPSON)Greenfield345 kV600 MW1.0 yrs64.3
Greenfield (UNKNOWN131929 - FORT THOMPSON)Greenfield345 kV600 MW1.0 yrs64.1
Greenfield (UNKNOWN132856 - FORT RANDALL)Greenfield230 kV300 MW1.0 yrs63.0
Greenfield (UNKNOWN132856 - FORT RANDALL)Greenfield230 kV300 MW1.0 yrs62.2
Greenfield (UNKNOWN131929 - FORT THOMPSON)Greenfield345 kV600 MW1.0 yrs62.0
Greenfield (UNKNOWN132434 - GAVINS POINT)Greenfield115 kV100 MW1.0 yrs61.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN132856 - FORT RANDALL), Knox County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.