Datacenter Sites in Carson City, Nevada
Carson City has 55 scored datacenter candidate sites averaging 45.9/100 DC Readiness, with a catalogued aggregate of 1,719 MW. FEMA rates local natural-hazard risk as "Very Low". The county has a datacenter tax incentive on record.
55
Candidate sites
45.9/100
Avg DC Readiness
1,719 MW
Catalogued capacity
theoretical aggregate
Very Low
Hazard rating
Site-selection context for Carson City
Yessales_tax_abatement
Datacenter tax incentive
5.83¢/kWh
Commercial electricity
5.01¢/kWh
Industrial electricity
6
Fiber providers
Extremely High
Water stress
$13,675
Land price / acre
2,000
Cooling degree days
3,700
Heating degree days
50°F
Mean annual temp
Incentive detail: Partial abatement of sales/use tax and personal property tax for $25M+ DC investments.
By site type
Top datacenter sites in Carson City
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| CARSON | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 62.1 |
| HEYBOURNE | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 61.9 |
| BRUNSWICK | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 61.6 |
| INCLINE | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 57.8 |
| PRISON HILL | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 57.2 |
| DAYTON | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 56.3 |
| Greenfield (BRUNSWICK - MT. ROSE) | Greenfield | 120 kV | 100 MW | 5.8 yrs | 56.1 |
| ROUND HILL | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 55.8 |
| Greenfield (TRACY - BRUNSWICK) | Greenfield | 120 kV | 100 MW | 5.8 yrs | 54.9 |
| Greenfield (BRUNSWICK - MT. ROSE) | Greenfield | 120 kV | 100 MW | 5.8 yrs | 54.7 |
| Greenfield (BUCKEYE - ROUND HILL) | Greenfield | 120 kV | 100 MW | 5.8 yrs | 53.6 |
| Greenfield (DAYTON - PRISON HILL) | Greenfield | 120 kV | 100 MW | 5.8 yrs | 53.1 |
| Greenfield (FORT CHURCHILL - BRUNSWICK) | Greenfield | 120 kV | 100 MW | 5.8 yrs | 52.5 |
| EC FFE Carson City | Greenfield | — | — | 5.8 yrs | 50.3 |
| Greenfield (DAYTON - PRISON HILL) | Greenfield | 120 kV | 100 MW | 5.8 yrs | 50.0 |
| Greenfield (BRUNSWICK - INCLINE) | Greenfield | 120 kV | 100 MW | 5.8 yrs | 49.9 |
| Greenfield (FORT CHURCHILL - BRUNSWICK) | Greenfield | 120 kV | 100 MW | 5.8 yrs | 49.6 |
| Farad | Brownfield | 120 kV | 3 MW | 5.7 yrs | 46.5 |
| Kings Beach | Brownfield | 120 kV | 16 MW | 5.7 yrs | 46.0 |
| Greenfield (BRUNSWICK - INCLINE) | Greenfield | 120 kV | 100 MW | 5.8 yrs | 45.5 |
| DWP - WALKER RIVER IRRIG PROJECT | Federal Excess | — | — | — | 43.6 |
| Old Hot Springs Road Vacant Property | Industrial | — | — | — | 42.2 |
| Old Hot Springs Road Vacant Property (Parcel #2) | Industrial | — | — | — | 42.2 |
| College Parkway Site | Industrial | — | — | — | 42.2 |
| 2800 Lockheed Way | Industrial | — | — | — | 42.2 |
Carson City datacenter FAQ
- How many datacenter sites are in Carson City?
- 55 scored datacenter candidate sites, averaging 45.9/100 DC Readiness.
- Does Carson City offer datacenter tax incentives?
- Partial abatement of sales/use tax and personal property tax for $25M+ DC investments.
- What is the natural-hazard risk in Carson City?
- FEMA's National Risk Index rates Carson City as "Very Low" (score 12).
- What are industrial electricity rates in Carson City?
- Average industrial electricity is 5.01¢/kWh and commercial is 5.83¢/kWh in Carson City.
Dataset updated . Screening estimates derived from public data sources.