Greenfield (UNKNOWN132759 - UNKNOWN137038)

Greenfield

Coos County, New Hampshire · ISO-NE

DC Readiness
55.5
Good / 100

Greenfield (UNKNOWN132759 - UNKNOWN137038) is a greenfield datacenter candidate site in Coos County, New Hampshire, interconnecting through ISO-NE. It screens at 55.5/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN132759
Substation voltage115 kV
Available capacity100 MW
LMP zoneISONE_VT
Wholesale LMP$69.07/MWh
Utility commercial rate0.15¢/kWh

Speed to power

ISO / RTO regionISO-NE
Queue depth3
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate25%
Withdrawal rate75%

Connectivity

Nearest IXPTech Vault South Burlington
IXP distance77.9 mi
Fiber providers5
Fiber coverage76.8%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance478.2 mi

Site characteristics

Site typeGreenfield
Parcel ownerPUBLIC SERVICE CO OF NH
Land owner typeprivate
Buildability75.0/100
Land cover (NLCD)Pasture/Hay

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteWHITEFIELD TRANSFER STATION
Hazard sub-score75/100
Construction cost index124.2 (avg 100)

Location context

Nearest datacenterTech Vault South Burlington
DC distance77.9 mi
Nearest rail1.1 mi
Nearest gas pipeline22.3 mi
Nearest fiber route6.6 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveNo
Commercial electricity15.16¢/kWh
Industrial electricity13.23¢/kWh
Cooling degree days400
Heating degree days7,200
Land price / acre$4,071

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power15%
55
Fiber connectivity12%
67
Energy cost10%
64
Water risk8%
93
Natural hazard8%
75
Buildability7%
75
Labor market4%
50
DC cluster4%
20
Land / acreage3%
64
Construction cost3%
47
Gas pipeline2%
28
Tax incentive2%
0
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Coos County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN132759 - UNKNOWN137038)
SiteTypeVoltageCapacityQueue waitScore
PONTOOK HYDRO FACILITYSubstation-Adjacent115 kV100 MW3.5 yrs64.7
LOST NATIONSubstation-Adjacent115 kV100 MW3.5 yrs64.5
UNKNOWN137036Substation-Adjacent115 kV100 MW3.5 yrs62.8
UNKNOWN137038Substation-Adjacent115 kV100 MW3.5 yrs62.5
TAP137032Substation-Adjacent115 kV100 MW3.5 yrs62.2
UNKNOWN137035Substation-Adjacent115 kV100 MW3.5 yrs61.0
UNKNOWN132759Substation-Adjacent115 kV100 MW3.5 yrs59.1
UNKNOWN132759Substation-Adjacent115 kV100 MW3.5 yrs56.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN132759 - UNKNOWN137038), Coos County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.