EC FFE De Baca County

Greenfield

De Baca County, New Mexico · SPP

DC Readiness
55.7
Good / 100

EC FFE De Baca County is a greenfield datacenter candidate site in De Baca County, New Mexico, interconnecting through SPP. It screens at 55.7/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneSPP_SOUTH
Wholesale LMP$15.62/MWh
Utility commercial rate0.16¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth24
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPSouthwest Cyberport Albuquerque
IXP distance134.3 mi
Fiber providers1
Fiber coverage93.2%
Nearest cloud providerAzure
Nearest cloud regionwestus3
Cloud region distance443.7 mi

Site characteristics

Site typeGreenfield
Parcel ownerPUBLIC SERVICE COMPANY OF NEW MEXICO
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub
Former usefossil fuel employment

Risk & environment

Flood zoneZone X
Water stress (WRI)4.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score85/100
Construction cost index83.6 (avg 100)

Location context

Nearest datacenterJohn F. Simms Building
DC distance126.8 mi
Nearest rail3.7 mi
Nearest gas pipeline5.8 mi
Nearest fiber route114.4 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveNo
Commercial electricity16.24¢/kWh
Industrial electricity9.23¢/kWh
Cooling degree days1,400
Heating degree days4,000
Land price / acre$385

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
47
Fiber connectivity12%
71
Energy cost10%
90
Water risk8%
49
Natural hazard8%
85
Buildability7%
70
Labor market4%
50
DC cluster4%
20
Land / acreage3%
55
Construction cost3%
80
Gas pipeline2%
82
Tax incentive2%
0
Climate / cooling2%
55

Nearby comparable sites

Other scored datacenter candidate sites in De Baca County, ranked by DC Readiness.

Sites near EC FFE De Baca County
SiteTypeVoltageCapacityQueue waitScore
TAIBAN MESASubstation-Adjacent345 kV600 MW3.4 yrs63.9
Greenfield (BLACKWATER TIE - TAIBAN MESA)Greenfield345 kV600 MW3.4 yrs59.7
Greenfield (TAIBAN MESA - GUADALUPE)Greenfield345 kV600 MW3.4 yrs59.7
Greenfield (BLACKWATER TIE - TAIBAN MESA)Greenfield345 kV600 MW3.4 yrs58.8
Greenfield (TAIBAN MESA - GUADALUPE)Greenfield345 kV600 MW3.4 yrs58.2
Greenfield (TAIBAN MESA - GUADALUPE)Greenfield345 kV600 MW3.4 yrs57.9
CARLSBADFederal Excess40.1
CARLSBADFederal Excess40.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.