UNKNOWN300314

Substation-Adjacent

Grant, New Mexico · SPP

DC Readiness
61.1
Good / 100

UNKNOWN300314 is a substation-adjacent datacenter candidate site in Grant, New Mexico, interconnecting through SPP. It screens at 61.1/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN300314
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zoneSPP_SOUTH
Wholesale LMP$15.62/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth24
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPMDC El Paso
IXP distance124.4 mi
Fiber providers2
Fiber coverage2.0%
Nearest cloud providerAzure
Nearest cloud regionwestus3
Cloud region distance234.6 mi

Site characteristics

Parcel ownerPUBLIC SERVICE COMPANY OF NEW MEXICO
Land owner typeprivate
Buildability100.0/100
Land cover (NLCD)Developed, High Intensity
Former usegas
Existing capacity48 MW
Retirement date2005-12-01

Risk & environment

Flood zoneZone X
Water stress (WRI)4.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteFORMER HURLEY SMELTER
Hazard sub-score75/100
Construction cost index62.6 (avg 100)

Location context

Nearest datacenterCenturyLink DC
DC distance85.4 mi
Nearest rail0.0 mi
Nearest gas pipeline1.4 mi
Nearest fiber route115.3 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveNo
Commercial electricity11.94¢/kWh
Industrial electricity6.15¢/kWh
Cooling degree days1,400
Heating degree days4,000
Land price / acre$575

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
50
Fiber connectivity12%
50
Energy cost10%
91
Water risk8%
48
Natural hazard8%
75
Buildability7%
100
Labor market4%
50
DC cluster4%
20
Land / acreage3%
55
Construction cost3%
98
Gas pipeline2%
95
Tax incentive2%
0
Climate / cooling2%
55

Nearby comparable sites

Other scored datacenter candidate sites in Grant, ranked by DC Readiness.

Sites near UNKNOWN300314
SiteTypeVoltageCapacityQueue waitScore
IVANHOESubstation-Adjacent115 kV100 MW3.5 yrs60.8
TYRONE (PHELPS DODGE)Substation-Adjacent115 kV100 MW3.5 yrs60.6
HIDALGOSubstation-Adjacent345 kV600 MW3.5 yrs59.2
Greenfield (HIDALGO - GREENLEE)Greenfield345 kV600 MW3.5 yrs59.1
Greenfield (LUNA - HIDALGO)Greenfield345 kV600 MW3.5 yrs59.1
Greenfield (HIDALGO - GREENLEE)Greenfield345 kV600 MW3.5 yrs58.6
MD #1Substation-Adjacent115 kV100 MW3.5 yrs58.5
Greenfield (LUNA - HIDALGO)Greenfield345 kV600 MW3.5 yrs58.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN300314, Grant. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.