Datacenter Sites in Chautauqua County, New York
Chautauqua County has 72 scored datacenter candidate sites averaging 49.5/100 DC Readiness, with a catalogued aggregate of 4,300 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
72
Candidate sites
49.5/100
Avg DC Readiness
4,300 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Chautauqua County
Yessales_tax_exemption
Datacenter tax incentive
7.92¢/kWh
Commercial electricity
4.72¢/kWh
Industrial electricity
10
Fiber providers
Low
Water stress
$3,536
Land price / acre
700
Cooling degree days
6,100
Heating degree days
46°F
Mean annual temp
Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.
By site type
Top datacenter sites in Chautauqua County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| S. RIPLEY | Substation-Adjacent | 230 kV | 300 MW | 3.0 yrs | 68.3 |
| TAP155788 | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 66.3 |
| CUMMINS | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 65.6 |
| UNKNOWN124347 | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 63.9 |
| TAP138728 | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 63.6 |
| BAKER ST | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 63.3 |
| TAP138732 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 62.4 |
| TAP160977 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 62.1 |
| Greenfield (S. RIPLEY - DUNKIRK) | Greenfield | 230 kV | 300 MW | 3.0 yrs | 62.0 |
| LUDIUM | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 61.6 |
| Greenfield (S. RIPLEY - DUNKIRK) | Greenfield | 230 kV | 300 MW | 3.0 yrs | 61.2 |
| HARTFIELD | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 60.9 |
| TAP146129 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 60.5 |
| SILVER CREEK | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 60.5 |
| TAP160989 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 60.3 |
| TAP146137 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 59.9 |
| DUNKIRK | Substation-Adjacent | 230 kV | 300 MW | 3.5 yrs | 59.9 |
| UNKNOWN146130 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 59.8 |
| Greenfield (GARDENVILLE - DUNKIRK) | Greenfield | 230 kV | 300 MW | 3.5 yrs | 58.6 |
| DEADEND166942 | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 58.4 |
| TAP140136 | Substation-Adjacent | 115 kV | 100 MW | 3.5 yrs | 58.3 |
| MOON SWITCHES | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 58.3 |
| TAP140136 | Substation-Adjacent | 115 kV | 100 MW | 3.0 yrs | 58.2 |
| Greenfield (TAP138728 - TAP140136) | Greenfield | 115 kV | 100 MW | 3.0 yrs | 57.9 |
| Greenfield (FALCONER - MOON SWITCHES) | Greenfield | 115 kV | 100 MW | 3.0 yrs | 56.9 |
Chautauqua County datacenter FAQ
- How many datacenter sites are in Chautauqua County?
- 72 scored datacenter candidate sites, averaging 49.5/100 DC Readiness.
- Does Chautauqua County offer datacenter tax incentives?
- Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.
- What is the natural-hazard risk in Chautauqua County?
- FEMA's National Risk Index rates Chautauqua County as "Relatively High" (score 35).
- What are industrial electricity rates in Chautauqua County?
- Average industrial electricity is 4.72¢/kWh and commercial is 7.92¢/kWh in Chautauqua County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Chautauqua County, New York. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.