Datacenter Sites in Montgomery County, New York

Montgomery County has 38 scored datacenter candidate sites averaging 56.1/100 DC Readiness, with a catalogued aggregate of 7,400 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.

38
Candidate sites
56.1/100
Avg DC Readiness
7,400 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating

Site-selection context for Montgomery County

Yessales_tax_exemption
Datacenter tax incentive
7.42¢/kWh
Commercial electricity
3.98¢/kWh
Industrial electricity
5
Fiber providers
Low
Water stress
$3,700
Land price / acre
700
Cooling degree days
6,100
Heating degree days
46°F
Mean annual temp

Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.

By site type

Top datacenter sites in Montgomery County

Top datacenter sites in Montgomery County
SiteTypeVoltageCapacityQueue waitScore
Greenfield (NEW SCOTLAND - MARCY)Greenfield345 kV600 MW3.5 yrs62.3
UNKNOWN127903Substation-Adjacent115 kV100 MW3.5 yrs61.1
TAP135941Substation-Adjacent115 kV100 MW3.5 yrs60.7
Greenfield (NEW SCOTLAND - EDIC)Greenfield345 kV600 MW3.5 yrs60.7
TAP141250Substation-Adjacent115 kV100 MW3.5 yrs60.7
Greenfield (ROTTERDAM - PORTER)Greenfield230 kV300 MW3.5 yrs60.4
TAP135943Substation-Adjacent115 kV100 MW3.5 yrs60.1
Greenfield (NEW SCOTLAND - MARCY)Greenfield345 kV600 MW3.5 yrs60.1
UNKNOWN127617Substation-Adjacent115 kV100 MW3.5 yrs59.8
UNKNOWN127909Substation-Adjacent115 kV100 MW3.5 yrs59.8
Greenfield (NEW SCOTLAND - EDIC)Greenfield345 kV600 MW3.5 yrs59.8
Greenfield (NEW SCOTLAND - EDIC)Greenfield345 kV600 MW3.5 yrs59.7
UNKNOWN127905Substation-Adjacent115 kV100 MW3.5 yrs59.1
TAP141258Substation-Adjacent115 kV100 MW3.5 yrs59.0
Greenfield (ROTTERDAM - PORTER)Greenfield230 kV300 MW3.5 yrs58.9
UNKNOWN127629Substation-Adjacent115 kV100 MW3.5 yrs58.9
TAP141259Substation-Adjacent115 kV100 MW3.5 yrs58.9
TAP135944Substation-Adjacent115 kV100 MW3.5 yrs58.8
Greenfield (NEW SCOTLAND - MARCY)Greenfield345 kV600 MW3.5 yrs58.6
TAP135940Substation-Adjacent115 kV100 MW3.5 yrs58.5
Greenfield (ROTTERDAM - PORTER)Greenfield230 kV300 MW3.5 yrs58.3
Greenfield (ROTTERDAM - PORTER)Greenfield230 kV300 MW3.5 yrs58.1
TAP135945Substation-Adjacent115 kV100 MW3.5 yrs57.9
Greenfield (ROTTERDAM - PORTER)Greenfield230 kV300 MW3.5 yrs57.8
UNKNOWN127904Substation-Adjacent115 kV100 MW3.5 yrs57.7

Montgomery County datacenter FAQ

How many datacenter sites are in Montgomery County?
38 scored datacenter candidate sites, averaging 56.1/100 DC Readiness.
Does Montgomery County offer datacenter tax incentives?
Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.
What is the natural-hazard risk in Montgomery County?
FEMA's National Risk Index rates Montgomery County as "Relatively High" (score 35).
What are industrial electricity rates in Montgomery County?
Average industrial electricity is 3.98¢/kWh and commercial is 7.42¢/kWh in Montgomery County.

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Montgomery County, New York. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.